Question

Current sizing involves developing some calculations and consulting some tables so that sufficient parameters can be defined for using the correct current for a given application. Suppose you are an engineer at a large company and need to determine the number of teeth on a pinion. Use the table below as a reference for the calculation. Do as requested. Current type Gear ratio 1 2 3 4 5 6 Roller chain 31 27 25 23 21 17 Table 1 - Selection of the number of pinion teeth Source: Adapted from Melconian (2019, p. 300). #PracegoVer: the table shows the definition of the number of teeth on the pinion. The first column has two lines, the first being “Chain type”, and the second, “Roller chain”. The second column contains three lines. The first line shows the “Transmission ratio”. The second line has six other columns: the first column contains the number “1”; the second, the number “2”; the third, the number “3”; the fourth, the number “5”; and the sixth, the number “6”. The second line of the “Transmission ratio” column contains six other columns, the first being “31”; the second “27”; the third “25”; the fourth “23”; the fifth “21”; and the sixth “17”. MELCONIAN, S. Machine Elements. 11th ed. According to the table, answer: a reducer is driven by a chain transmission, driven by an electric motor with a power of 22 kW and rotation n = 1180 rpm. The input shaft rotation is 600 rpm. The permitted center distance is 500 mm. Consider a chain pitch of 5/8” and the use of roller chains with vp (peripheral speed) limited to 12 m/s. Calculate: a) the number of pinion teeth (Z1); b) the number of teeth on the crown (Z2); c) peripheral speed (vp); d) the tangential force (FT) in Newton; e) checking the distance between centers (C); f) the number of links in the chain (y); and g) the length of the chain (l).

154

likes
770 views

Answer to a math question Current sizing involves developing some calculations and consulting some tables so that sufficient parameters can be defined for using the correct current for a given application. Suppose you are an engineer at a large company and need to determine the number of teeth on a pinion. Use the table below as a reference for the calculation. Do as requested. Current type Gear ratio 1 2 3 4 5 6 Roller chain 31 27 25 23 21 17 Table 1 - Selection of the number of pinion teeth Source: Adapted from Melconian (2019, p. 300). #PracegoVer: the table shows the definition of the number of teeth on the pinion. The first column has two lines, the first being “Chain type”, and the second, “Roller chain”. The second column contains three lines. The first line shows the “Transmission ratio”. The second line has six other columns: the first column contains the number “1”; the second, the number “2”; the third, the number “3”; the fourth, the number “5”; and the sixth, the number “6”. The second line of the “Transmission ratio” column contains six other columns, the first being “31”; the second “27”; the third “25”; the fourth “23”; the fifth “21”; and the sixth “17”. MELCONIAN, S. Machine Elements. 11th ed. According to the table, answer: a reducer is driven by a chain transmission, driven by an electric motor with a power of 22 kW and rotation n = 1180 rpm. The input shaft rotation is 600 rpm. The permitted center distance is 500 mm. Consider a chain pitch of 5/8” and the use of roller chains with vp (peripheral speed) limited to 12 m/s. Calculate: a) the number of pinion teeth (Z1); b) the number of teeth on the crown (Z2); c) peripheral speed (vp); d) the tangential force (FT) in Newton; e) checking the distance between centers (C); f) the number of links in the chain (y); and g) the length of the chain (l).

Expert avatar
Jett
4.7
97 Answers
a) The gear ratio can be calculated using:

i = \frac{n_1}{n_2} = \frac{1180}{600} \approx 1.9667

Look up the gear ratio in the table. For a ratio of approximately 2, the number of pinion teeth $Z_1$ is:

Z_1 = 27

b) The number of teeth on the crown can be calculated by:

Z_2 = Z_1 \times i \approx 27 \times 1.9667 \approx 54

c) The peripheral speed $vp$ can be calculated using:

v_p = \frac{Z_1 \cdot n_2 \cdot \pi \cdot P}{60 \times 1000}

v_p = \frac{27 \times 600 \times \pi \times \frac{5}{8}}{60 \times 1000} \approx 11.02 \, \text{m/s}

d) The tangential force $F_T$ can be calculated as:

F_T = \frac{P}{v_p}

F_T = \frac{22 \times 1000}{11.02} \approx 1987.43 \, \text{N}

e) The center distance $C$ can be calculated approximately by:

C = \frac{P}{2\pi} (Z_1 + Z_2)

C \approx 500 \, \text{mm}

f) Chain links $y$ can be approximated by:

y = \frac{2C}{P} + \frac{Z_2 + Z_1}{2}

Assuming $y \approx 50$

g) The length of the chain $l$ can be calculated as:

l = y \times P

l \approx 1538.6 \, \text{mm}

Frequently asked questions (FAQs)
What is the equation of a parabola that opens upwards, has a vertex at (2,5), and passes through the point (4,9)?
+
Question: In a right triangle, given the angle A = 30° and the length of adjacent side AB = 10 units. Find the length of the opposite side.
+
What is the equation for the median of a triangle with side lengths 6, 8, and 10?
+
New questions in Mathematics
Find an arc length parameterization of the curve that has the same orientation as the given curve and for which the reference point corresponds to t=0. Use an arc length s as a parameter. r(t) = 3(e^t) cos (t)i + 3(e^t)sin(t)j; 0<=t<=(3.14/2)
Let 𝑢 = 𝑓(𝑥, 𝑦) = (𝑒^𝑥)𝑠𝑒𝑛(3𝑦). Check if 9((𝜕^2) u / 𝜕(𝑥^2)) +((𝜕^2) 𝑢 / 𝜕(𝑦^2)) = 0
CASE 6-1: PREPARE A PRODUCTION PLAN: WHAT PROBLEMS ARRIVE? Midwest Plastics Company has conducted profit planning for several years. The president stated (with justification) that inventory control and planning had not been satisfactory, which was mainly due to poor planning of production and inventory budgets. Please analyze and provide recommendations, in detail, on the issue regarding the 20B profit plan, which is now being prepared. Their analysis and recommendations will be presented to the executive committee. Despite the seasonality factor, the sales department has been successful in developing a sales plan, on a monthly basis, for each year. The following sales data is available for 20B. 1. Sales plan summary for 20B: 2. Finished goods inventory, as of January 1, 20B, is 96,000 units. 3. Work-in-process inventory will remain constant. 4. Actual annual sales in 20A, including the estimate for December, were 350,000 units. 5. The average finished goods inventory during 20A was 70,000 units. IT IS REQUESTED. 1. Prepare the annual production budget, assuming that management policy is to budget ending finished goods inventory at a standard quantity, based on the ratio of historical sales of 20A to inventory turnover. 2. Prepare a schedule showing sales, production, and inventory levels for each month, assuming: 1) stable inventory, 2) stable production, and 3) recommended inventory-production levels. In developing your recommendations, assume that the following policies have been established: a) The president has set the policy that a maximum inventory of 85,000 units and a minimum inventory of 75,000 units should be used, except in abnormal circumstances. b) A stable level of production is definitely preferred, except that during the holiday season in July and August, production may be reduced by 25 percent. Likewise, a variation in production of 7.5 percent above and below the average level is acceptable. 3. What are the main problems faced by the company in production planning? Make your general recommendations.
5(4x+3)=75
the value of sin 178°58&#39;
A car that starts from rest moves for 11 min, reaching a speed of 135 km/h, calculate the acceleration it had
3x+5y=11 2x-3y=1
The length and breadth of my rectangular vegetable garden is 12,5m and 7,25m respectively. What is the perimeter of the garden?
How long will it take for $900 to become $5000 at an annual rate of 11.15% compounded bimonthly?
2x2 and how much?
find x in the equation 2x-4=6
20% of 3500
What is 75 percent less than 60
Sections of steel tube having an inside diameter of 9 inches, are filled with concrete to support the main floor girder in a building. If these posts are 12 feet long and there are 18 of them, how many cubic yards of concrete are required for the job?
A hardware bill totals $857.63 with discounts of 5% and 3%. What is the net cost of the Material ?
17. A loan for $104259 is taken out for 10 years with an annual interest rate of 9.4%, compounded quarterly. What quarterly payment is required to pay the loan off in 10 years? Enter to the nearest cent (two decimals). Do not use $ signs or commas in the answer.
A factory produces glass for windows. The thickness X of an arbitrarily selected pane of glass is assumed to be Normally distributed with expectation μ = 4.10 and standard deviation σ = 0.04. Expectation and Standard deviation is measured in millimeters. What is the probability that an arbitrary route has a thickness less than 4.00 mm?
The mean of 4 numbers is 5 and the mean of 3 different numbers is 12. What is the mean of the 7 numbers together? Produce an algebraic solution. Guess and check is acceptable.
question 1 Consider a sample space S, and two events A and B such that P(A ∩ B) = 0.2, P(A ∪ B) = 0.6, P(B ∪ ̄A) = 0.8 (a) [0.5 points] Calculate P (A). (b) [0.5 points] Calculate P (B)
-Please answer to the following questions: What is the price elasticity of demand? Can you explain it in your own words? What is the price elasticity of supply? Can you explain it in your own words? What is the relationship between price elasticity and position on the demand curve? For example, as you move up the demand curve to higher prices and lower quantities, what happens to the measured elasticity? How would you explain that? B-Assume that the supply of low-skilled workers is fairly elastic, but the employers’ demand for such workers is fairly inelastic. If the policy goal is to expand employment for low-skilled workers, is it better to focus on policy tools to shift the supply of unskilled labor or on tools to shift the demand for unskilled labor? What if the policy goal is to raise wages for this group? Explain your answers with supply and demand diagrams. Make sure to properly cite and reference your academic or peer-reviewed sources (minimum 2).