Question

A crawler hoe having a 2.5-cy bucket and whose cost per hour, including the wages to an operator, is $109 will excavate and load haul units under the stated conditions as - depth of excavation is 12 feet, angle of swing is 80 degrees, percent swell is 14 and efficiency factor is 55 min per hour. The maximum digging depth of the machine is 22 feet. Use load bucket time 6 sec; swing loaded time 6 sec; dump bucket time 4 sec and swing empty time 5 sec. Determine the cost per bank cubic yard for the material sand and gravel. Show all the calculations with all the required checking.

86

likes
432 views

Answer to a math question A crawler hoe having a 2.5-cy bucket and whose cost per hour, including the wages to an operator, is $109 will excavate and load haul units under the stated conditions as - depth of excavation is 12 feet, angle of swing is 80 degrees, percent swell is 14 and efficiency factor is 55 min per hour. The maximum digging depth of the machine is 22 feet. Use load bucket time 6 sec; swing loaded time 6 sec; dump bucket time 4 sec and swing empty time 5 sec. Determine the cost per bank cubic yard for the material sand and gravel. Show all the calculations with all the required checking.

Expert avatar
Fred
4.4
117 Answers
To calculate the cost per bank cubic yard for the material sand and gravel, we need to consider the following steps:

1. Calculate the bucket capacity in bank cubic yards (BCY):
Given bucket capacity = 2.5 cubic yards
Percent swell = 14%
Bucket capacity in BCY = bucket capacity / (1 + swell/100)
Bucket capacity in BCY = 2.5 / (1 + 14/100) = 2.19 BCY

2. Determine the bank cubic yards per load:
Given depth of excavation = 12 feet
Maximum digging depth of the machine = 22 feet
Bank cubic yards per foot = 1
Bank cubic yards per load = depth of excavation * 2 * bucket capacity in BCY
Bank cubic yards per load = 12 * 2 * 2.19 = 52.56 BCY

3. Calculate the cycle time in minutes:
Given load bucket time = 6 sec
Given swing loaded time = 6 sec
Given dump bucket time = 4 sec
Given swing empty time = 5 sec
Cycle time = (load bucket time + swing loaded time + dump bucket time + swing empty time) / 60
Cycle time = (6 + 6 + 4 + 5) / 60 = 0.2167 hours

4. Determine the production rate in bank cubic yards per hour:
Given efficiency factor = 55% = 0.55
Production rate = 60 / cycle time * efficiency factor
Production rate = 60 / 0.2167 * 0.55 = 151.29 BCY/hr

5. Calculate the operating cost per bank cubic yard:
Given cost per hour = 109Operating cost per bank cubic yard = cost per hour / production rateOperating cost per bank cubic yard = 109 / 151.29 = 0.72 per BCY

### Answer
The cost per bank cubic yard for the material sand and gravel is 0.72$ per BCY.

Frequently asked questions (FAQs)
What is the variance of the following set of numbers: 6, 8, 9, 10, 12?
+
What is the value of f(x) when x = 3?
+
What is the period of the function y = cot(x)?
+
New questions in Mathematics
Let 𝑒 = 𝑓(π‘₯, 𝑦) = (𝑒^π‘₯)𝑠𝑒𝑛(3𝑦). Check if 9((πœ•^2) u / πœ•(π‘₯^2)) +((πœ•^2) 𝑒 / πœ•(𝑦^2)) = 0
what is 9% of 307
In a random sample of 600 families in the Metropolitan Region that have cable television service, it is found that 460 are subscribed to the Soccer Channel (CDF). How large a sample is required to be if we want to be 95% confident that the estimate of β€œp” is within 0.03?
2x+4x=
sin 30
6-35 A recent study by an environmental watchdog determined that the amount of contaminants in Minnesota lakes (in parts per million) it has a normal distribution with a mean of 64 ppm and variance of 17.6. Assume that 35 lakes are randomly selected and sampled. Find the probability that the sample average of the amount of contaminants is a) Greater than 72 ppm. b) Between 64 and 72 ppm. c) Exactly 64 ppm. d) Greater than 94 ppm.
Exercise 1 An ejidal association wishes to determine the distribution for the three different crops that it can plant for the next season on its available 900 hectares. Information on the total available and how many resources are required for each hectare of cultivation is shown in the following tables: Total available resource Water 15,000 m3 Fertilizer 5,000 kg Labor 125 day laborers Requirements per cultivated hectare Corn Soybeans Wheat Water 15 25 20 Fertilizer 5 8 7 Labor** 1/8 1/5 1/4 *The data in fraction means that with one day laborer it will be possible to care for 8, 5 and 4 hectares respectively. * Sales of crops 1 and 3, according to information from the Department of Agriculture, are guaranteed and exceed the capacity of the cooperative. However, soybeans must be limited to a maximum of 150 hectares. On the other hand, the profits for each hectare of crop obtained are estimated at: $7,500 for corn, $8,500 for soybeans and $8,000 for wheat. The objectives are to determine: β€’ How many hectares of each crop must be allocated so that the profit is maximum. R= β€’ The estimated profits for the ejidal cooperative in the next growing season. R=
4+168Γ—10Β³Γ—d1+36Γ—10Β³Γ—d2=-12 -10+36Γ—10Β³Γ—d1+72Γ—10Β³Γ—d2=0
Two minus log 3X equals log (X over 12)
A teacher has 25 red and yellow counters altogether. She has 4 times as many red counters than yellow counters. How many yellow counters does the teacher have?
Solve equations by equalization method X-8=-2y 2x+y=7
Show work on 4108 divided by 4
2.380Γ— (1+0.05) / 0.95βˆ’0.05
viii. An ac circuit with a 80 ΞΌF capacitor in series with a coil of resistance 16Ω and inductance 160mH is connected to a 100V, 100 Hz supply is shown below. Calculate 7. the inductive reactance 8. the capacitive reactance 9. the circuit impedance and V-I phase angle ΞΈ 10. the circuit current I 11. the phasor voltages VR, VL, VC and VS 12. the resonance circuit frequency Also construct a fully labeled and appropriately β€˜scaled’ voltage phasor diagram.
Which statement best describes the key changes in perspectives on inclusion? An inclusive program must consider the unique experiences of every child and family as well as the child's strengths and needs. There is a shift in thinking about individual programs as "inclusive programs" to thinking about inclusion as something that reflects the cultural influence of the family. There is a greater emphasis on barriers to full participation and the acknowledgement that all children are unique and must be fully and meaningfully engaged in a program. In an inclusive program all participants are accepted by their peers and other members of the community.
Calculate the area of the parallelogram with adjacent vertices (1,4, βˆ’2), (βˆ’3,1,6) 𝑦 (1, βˆ’2,3)
If the mean of the following numbers is 17, find the c value. Produce an algebraic solution. Guess and check is unacceptable. 12, 18, 21, c, 13
The mean of 4 numbers is 5 and the mean of 3 different numbers is 12. What is the mean of the 7 numbers together? Produce an algebraic solution. Guess and check is acceptable.
A group of 17 people spent 9 days on vacation and spent R$776.34 on barbecue meat and the bill needs to be divided as follows: 6 people stayed for 9 days, 7 people stayed for 4 days, and 2 people stayed for 5 days and 2 people stayed 3 days, how much does each group have to pay for the days they stayed?
12[4 + (8 + 7) + 5]