Question

A crawler hoe having a 2.5-cy bucket and whose cost per hour, including the wages to an operator, is $109 will excavate and load haul units under the stated conditions as - depth of excavation is 12 feet, angle of swing is 80 degrees, percent swell is 14 and efficiency factor is 55 min per hour. The maximum digging depth of the machine is 22 feet. Use load bucket time 6 sec; swing loaded time 6 sec; dump bucket time 4 sec and swing empty time 5 sec. Determine the cost per bank cubic yard for the material sand and gravel. Show all the calculations with all the required checking.

86

likes
432 views

Answer to a math question A crawler hoe having a 2.5-cy bucket and whose cost per hour, including the wages to an operator, is $109 will excavate and load haul units under the stated conditions as - depth of excavation is 12 feet, angle of swing is 80 degrees, percent swell is 14 and efficiency factor is 55 min per hour. The maximum digging depth of the machine is 22 feet. Use load bucket time 6 sec; swing loaded time 6 sec; dump bucket time 4 sec and swing empty time 5 sec. Determine the cost per bank cubic yard for the material sand and gravel. Show all the calculations with all the required checking.

Expert avatar
Fred
4.4
118 Answers
To calculate the cost per bank cubic yard for the material sand and gravel, we need to consider the following steps:

1. Calculate the bucket capacity in bank cubic yards (BCY):
Given bucket capacity = 2.5 cubic yards
Percent swell = 14%
Bucket capacity in BCY = bucket capacity / (1 + swell/100)
Bucket capacity in BCY = 2.5 / (1 + 14/100) = 2.19 BCY

2. Determine the bank cubic yards per load:
Given depth of excavation = 12 feet
Maximum digging depth of the machine = 22 feet
Bank cubic yards per foot = 1
Bank cubic yards per load = depth of excavation * 2 * bucket capacity in BCY
Bank cubic yards per load = 12 * 2 * 2.19 = 52.56 BCY

3. Calculate the cycle time in minutes:
Given load bucket time = 6 sec
Given swing loaded time = 6 sec
Given dump bucket time = 4 sec
Given swing empty time = 5 sec
Cycle time = (load bucket time + swing loaded time + dump bucket time + swing empty time) / 60
Cycle time = (6 + 6 + 4 + 5) / 60 = 0.2167 hours

4. Determine the production rate in bank cubic yards per hour:
Given efficiency factor = 55% = 0.55
Production rate = 60 / cycle time * efficiency factor
Production rate = 60 / 0.2167 * 0.55 = 151.29 BCY/hr

5. Calculate the operating cost per bank cubic yard:
Given cost per hour = 109Operating cost per bank cubic yard = cost per hour / production rateOperating cost per bank cubic yard = 109 / 151.29 = 0.72 per BCY

### Answer
The cost per bank cubic yard for the material sand and gravel is 0.72$ per BCY.

Frequently asked questions (FAQs)
What is the maximum value of the function f(x) = 2x^2 - 5x + 3 over the interval [-1, 3]?
+
What is the standard deviation of a data set: 12, 15, 18, 20, 22,
+
What is the sine of an angle A if the cosine of angle B is 0.5? (
+
New questions in Mathematics
A car tire can rotate at a frequency of 3000 revolutions per minute. Given that a typical tire radius is 0.5 m, what is the centripetal acceleration of the tire?
(x^2+3x)/(x^2-9)=
What is the coefficient of elasticity of the material that must be placed on the heel of the 10 cm high clog, with a base area of 2 cmΒ² so that it deforms only 2 cm when the force on it will be a maximum of 600 N.
what is 9% of 307
solve the following trigo equation for 0Β°<= x <= 360Β°. sec x =-2
x/20*100
4x567
All the liquid contained in a barrel is distributed into 96 equal glasses up to its maximum capacity. We want to pour the same amount of liquid from another barrel identical to the previous one into glasses identical to those used, but only up to 3/4 of its capacity. How many more glasses will be needed for this?
(5u + 6)-(3u+2)=
Identify a pattern in the list of numbers.Then use this pattern to find the next number. 37,31,25,19,13
is the x element (180,270), if tanx-3cotx=2, sinx ?
2x2 and how much?
-3(-4x+5)=-6(7x-8)+9-10x
A study reports the following final notation: F (3, 32) = 9.50, p < .05. How many total participants were involved in this study? Group of answer choices 34 32 36
I want you to solve this problem as a grade sixth pupil in primary school: 8 Pigs ate 6 bags of fee in 20 days. How long will it take 10 pigs to eat 15 bags of feed eating at the same rate?
The price per night of a suite at the Baglioni Hotel in Venice is 1896 euros, VAT included. The VAT in Italy is 25%. The hotel gets a return of 10% out of the price VAT included. b) What is the profit value made by the hotel for one
The probability of growing a seedling from a seed is 0.62. How many seeds do I need to plant so that the probability of growing at least one seedling is greater than or equal to 0.87?
Find the vertex F(x)=x^2-10x
Find I (Intrest) using simple interest formula of 17700 @ 15% for 4 years
t+72/t=-17