Question

A crawler hoe having a 2.5-cy bucket and whose cost per hour, including the wages to an operator, is $109 will excavate and load haul units under the stated conditions as - depth of excavation is 12 feet, angle of swing is 80 degrees, percent swell is 14 and efficiency factor is 55 min per hour. The maximum digging depth of the machine is 22 feet. Use load bucket time 6 sec; swing loaded time 6 sec; dump bucket time 4 sec and swing empty time 5 sec. Determine the cost per bank cubic yard for the material sand and gravel. Show all the calculations with all the required checking.

86

likes
432 views

Answer to a math question A crawler hoe having a 2.5-cy bucket and whose cost per hour, including the wages to an operator, is $109 will excavate and load haul units under the stated conditions as - depth of excavation is 12 feet, angle of swing is 80 degrees, percent swell is 14 and efficiency factor is 55 min per hour. The maximum digging depth of the machine is 22 feet. Use load bucket time 6 sec; swing loaded time 6 sec; dump bucket time 4 sec and swing empty time 5 sec. Determine the cost per bank cubic yard for the material sand and gravel. Show all the calculations with all the required checking.

Expert avatar
Fred
4.4
120 Answers
To calculate the cost per bank cubic yard for the material sand and gravel, we need to consider the following steps:

1. Calculate the bucket capacity in bank cubic yards (BCY):
Given bucket capacity = 2.5 cubic yards
Percent swell = 14%
Bucket capacity in BCY = bucket capacity / (1 + swell/100)
Bucket capacity in BCY = 2.5 / (1 + 14/100) = 2.19 BCY

2. Determine the bank cubic yards per load:
Given depth of excavation = 12 feet
Maximum digging depth of the machine = 22 feet
Bank cubic yards per foot = 1
Bank cubic yards per load = depth of excavation * 2 * bucket capacity in BCY
Bank cubic yards per load = 12 * 2 * 2.19 = 52.56 BCY

3. Calculate the cycle time in minutes:
Given load bucket time = 6 sec
Given swing loaded time = 6 sec
Given dump bucket time = 4 sec
Given swing empty time = 5 sec
Cycle time = (load bucket time + swing loaded time + dump bucket time + swing empty time) / 60
Cycle time = (6 + 6 + 4 + 5) / 60 = 0.2167 hours

4. Determine the production rate in bank cubic yards per hour:
Given efficiency factor = 55% = 0.55
Production rate = 60 / cycle time * efficiency factor
Production rate = 60 / 0.2167 * 0.55 = 151.29 BCY/hr

5. Calculate the operating cost per bank cubic yard:
Given cost per hour = 109Operating cost per bank cubic yard = cost per hour / production rateOperating cost per bank cubic yard = 109 / 151.29 = 0.72 per BCY

### Answer
The cost per bank cubic yard for the material sand and gravel is 0.72$ per BCY.

Frequently asked questions (FAQs)
Question: What is the maximum value of the cube root function, y = ∛x, for x ≤ 27?
+
Question: Find the maximum value of a continuous function f(x) = 3x^2 + 5x - 2 in the interval [0, 2].
+
What is the probability of drawing a heart from a deck of cards?
+
New questions in Mathematics
𝑦 = ( 𝑥2 − 3) (𝑥3 + 2 𝑥 + 1)
The sum of an infinite geometric series is 13,5 The sum of the same series, calculated from the third term is 1,5. Q. Calculate r if r>0.
the value of sin 178°58'
A consulting company charges a fee of $50 per hour for consulting. If their monthly fixed costs are $1,000 and they want to make a monthly profit of $2,500, how many consulting hours should they bill per month?
7273736363-8
Suppose X has a Poisson distribution, with a mean of 0.4. Determine the probability that x is at most 2.
9b^2-6b-5
calculate the normal vector of line y = -0.75x + 3
determine the polynomial F of degree 2 that interpolates. f at points (0;1) (2;5) (4;6). calculate F(0.8). Note: Using the polynomial expression with difference operator.
Determine the reduced form of the slope equation equal to 2
3%2B2
A company has had the following data for two consecutive years. Total, asset item 3,100,500 euros 3,300,550 euros. Net amount of business figures 4,755,250 euros /5,100 euros Average number of workers employed during the year 64/70 You can present a balance sheet in an abbreviated form
Find the equation of a straight line that has slope 3 and passes through the point of (1, 7) . Write the equation of the line in general forms
Gender and communication : Answer the question ( 1 paragraph is ok) . Please can you write about women? Compared to your other identities, how much of a role does gender play in your life? And has your own sex/gender offered you privileges or disadvantages? How so?
Cuboid containers (open at the top) should be examined with regard to their volume. The figure below shows a network of such containers (x ∈ Df). Determine a function ƒ (assignment rule and definition area D) that describes the volume of these containers and calculate the volume of such a container if the content of the base area is 16 dm². Show that this function f has neither a local maximum nor a global maximum
Evaluate ab+dc if a=56 , b=−34 , c=0.4 , and d=12 . Write in simplest form.
2x-4=8
The inner radius of a spherical ball is 13 cm. How many liters of air are in it? Justify your answer!
Write an equation of the affine function whose graph is perpendicular to the graph of f(x) = 5x − 1 and passes through the point (5, 20).
A plant found at the bottom of a lake doubles in size every 10 days. Yeah It is known that in 300 days it has covered the entire lake, indicate how many days it will take to cover the entire lake four similar plants.