Question

A crawler hoe having a 2.5-cy bucket and whose cost per hour, including the wages to an operator, is $109 will excavate and load haul units under the stated conditions as - depth of excavation is 12 feet, angle of swing is 80 degrees, percent swell is 14 and efficiency factor is 55 min per hour. The maximum digging depth of the machine is 22 feet. Use load bucket time 6 sec; swing loaded time 6 sec; dump bucket time 4 sec and swing empty time 5 sec. Determine the cost per bank cubic yard for the material sand and gravel. Show all the calculations with all the required checking.

86

likes
432 views

Answer to a math question A crawler hoe having a 2.5-cy bucket and whose cost per hour, including the wages to an operator, is $109 will excavate and load haul units under the stated conditions as - depth of excavation is 12 feet, angle of swing is 80 degrees, percent swell is 14 and efficiency factor is 55 min per hour. The maximum digging depth of the machine is 22 feet. Use load bucket time 6 sec; swing loaded time 6 sec; dump bucket time 4 sec and swing empty time 5 sec. Determine the cost per bank cubic yard for the material sand and gravel. Show all the calculations with all the required checking.

Expert avatar
Fred
4.4
118 Answers
To calculate the cost per bank cubic yard for the material sand and gravel, we need to consider the following steps:

1. Calculate the bucket capacity in bank cubic yards (BCY):
Given bucket capacity = 2.5 cubic yards
Percent swell = 14%
Bucket capacity in BCY = bucket capacity / (1 + swell/100)
Bucket capacity in BCY = 2.5 / (1 + 14/100) = 2.19 BCY

2. Determine the bank cubic yards per load:
Given depth of excavation = 12 feet
Maximum digging depth of the machine = 22 feet
Bank cubic yards per foot = 1
Bank cubic yards per load = depth of excavation * 2 * bucket capacity in BCY
Bank cubic yards per load = 12 * 2 * 2.19 = 52.56 BCY

3. Calculate the cycle time in minutes:
Given load bucket time = 6 sec
Given swing loaded time = 6 sec
Given dump bucket time = 4 sec
Given swing empty time = 5 sec
Cycle time = (load bucket time + swing loaded time + dump bucket time + swing empty time) / 60
Cycle time = (6 + 6 + 4 + 5) / 60 = 0.2167 hours

4. Determine the production rate in bank cubic yards per hour:
Given efficiency factor = 55% = 0.55
Production rate = 60 / cycle time * efficiency factor
Production rate = 60 / 0.2167 * 0.55 = 151.29 BCY/hr

5. Calculate the operating cost per bank cubic yard:
Given cost per hour = 109Operating cost per bank cubic yard = cost per hour / production rateOperating cost per bank cubic yard = 109 / 151.29 = 0.72 per BCY

### Answer
The cost per bank cubic yard for the material sand and gravel is 0.72$ per BCY.

Frequently asked questions (FAQs)
What are the roots of the quadratic equation x² + 5x - 6 = 0?
+
What is the product of the square root of 2 and the sum of 5x and 3?
+
What is the measure of the missing angle in a right triangle with angles measuring 30° and 90°?
+
New questions in Mathematics
a to the power of 2 minus 16 over a plus 4, what is the result?
12-6x=4x+2
3(2+x)-2(2x+6)=20-4x
What payment 7 months from now would be equivalent in value to a $3,300 payment due 23 months from now? The value of money is 2.7% simple interest. Round your answer to 2 decimal places. Show all work and how you arrive at the answer..
A client did not advance L 10,000 for the rental of a parking area and it corresponds to 4 months, of which 2 months were consumed
Elliot opened a savings account and deposited $5000.00 as principal. The account earns 4% interest, compounded annually. How much interest will he earn after 5 years? Round your answer to the nearest cent.
Moaz wanted to test whether the level of headache pain (on a scale of 1 – 10) changes after taking Advil. He collected data from 9 participants and calculated the difference in headache pain before and after taking Advil (summarized in the table below). Determine W observed for this test. Difference Scores -2 -4 0 +1 +3 -2 0 -3 -5 Also, What is the degrees of freedom for this test?
find all matrices that commute with the matrix A=[0 1]
Suppose that you use 4.29 g of Iron in the chemical reaction: 2Fe(s) + 3 Cu2 + (aq) 2Fe 3 + (aq) + 3Cu(s ) - . What is the theoretical yield of Cu (s), in grams?
Shows two blocks, masses 4.3 kg and 5.4 kg, being pushed across a frictionless surface by a 22.5-N horizontal force applied to the 4.3-kg block. A. What is the acceleration of the blocks? B. What is the force of the 4.3-kg block on the 5.4 -kg block? C. What is the force of the 5.4 -kg block on the 4.3 -kg block?
1. A capital of $3,831 was lent, and it has produced interest of $840 from 05-12-2022 to 1-12-2023. At what annual simple interest rate was the capital lent?
Sabendo+que+o+tri%C3%A2ngulo+ABC+%C3%A9+ret%C3%A2ngulo+e+que+um+de+seus+%C3%A2ngulos+mede+30+quanto+mede+o+terceiro+ tri%C3%A2ngulo
(X+2)(x+3)=4x+18
Let f and g be defined in R and suppose that there exists M > 0 such that |f(x) − f(p)| ≤ M|g(x) − g(p)|, for all x. Prove that if g is continuous in p, then f will also be continuous in p.
Solve for B write your answer as a fraction or as a whole number. B-1/7=4
A property sold for $745,000 in a co-brokered transaction. The seller has agreed to pay a 7% commission to the listing firm. The listing firm has agreed to equally split the commission with the selling firm. If the buyer’s broker will receive 8% of the selling firm’s commission, how much commission will the buyer’s broker receive? $14,900 $3725 $$37250 $18625
What is the percentage of nitrogen abundance in copper dinatrate Cu(NO3)2
a coffee shop has 9 types of creamer and 11 types of sweetener. In how any ways can a person make their coffee?
Sally’s sales for last Sunday were $1,278. That was an increase of 6.5% over her sales for the previous Saturday. What were her sales for the previous Saturday?
t+72/t=-17