Question

A crawler hoe having a 2.5-cy bucket and whose cost per hour, including the wages to an operator, is $109 will excavate and load haul units under the stated conditions as - depth of excavation is 12 feet, angle of swing is 80 degrees, percent swell is 14 and efficiency factor is 55 min per hour. The maximum digging depth of the machine is 22 feet. Use load bucket time 6 sec; swing loaded time 6 sec; dump bucket time 4 sec and swing empty time 5 sec. Determine the cost per bank cubic yard for the material sand and gravel. Show all the calculations with all the required checking.

86

likes
432 views

Answer to a math question A crawler hoe having a 2.5-cy bucket and whose cost per hour, including the wages to an operator, is $109 will excavate and load haul units under the stated conditions as - depth of excavation is 12 feet, angle of swing is 80 degrees, percent swell is 14 and efficiency factor is 55 min per hour. The maximum digging depth of the machine is 22 feet. Use load bucket time 6 sec; swing loaded time 6 sec; dump bucket time 4 sec and swing empty time 5 sec. Determine the cost per bank cubic yard for the material sand and gravel. Show all the calculations with all the required checking.

Expert avatar
Fred
4.4
115 Answers
To calculate the cost per bank cubic yard for the material sand and gravel, we need to consider the following steps:

1. Calculate the bucket capacity in bank cubic yards (BCY):
Given bucket capacity = 2.5 cubic yards
Percent swell = 14%
Bucket capacity in BCY = bucket capacity / (1 + swell/100)
Bucket capacity in BCY = 2.5 / (1 + 14/100) = 2.19 BCY

2. Determine the bank cubic yards per load:
Given depth of excavation = 12 feet
Maximum digging depth of the machine = 22 feet
Bank cubic yards per foot = 1
Bank cubic yards per load = depth of excavation * 2 * bucket capacity in BCY
Bank cubic yards per load = 12 * 2 * 2.19 = 52.56 BCY

3. Calculate the cycle time in minutes:
Given load bucket time = 6 sec
Given swing loaded time = 6 sec
Given dump bucket time = 4 sec
Given swing empty time = 5 sec
Cycle time = (load bucket time + swing loaded time + dump bucket time + swing empty time) / 60
Cycle time = (6 + 6 + 4 + 5) / 60 = 0.2167 hours

4. Determine the production rate in bank cubic yards per hour:
Given efficiency factor = 55% = 0.55
Production rate = 60 / cycle time * efficiency factor
Production rate = 60 / 0.2167 * 0.55 = 151.29 BCY/hr

5. Calculate the operating cost per bank cubic yard:
Given cost per hour = 109Operating cost per bank cubic yard = cost per hour / production rateOperating cost per bank cubic yard = 109 / 151.29 = 0.72 per BCY

### Answer
The cost per bank cubic yard for the material sand and gravel is 0.72$ per BCY.

Frequently asked questions (FAQs)
Find the sum and product of two numbers if their sum is 10 and their product is 21.
+
What is the integral of x^2 from 0 to 4?
+
What is the square root of 2500?
+
New questions in Mathematics
Let f(x)=||x|−6|+|15−|x|| . Then f(6)+f(15) is equal to:
Calculate the 6th term of PA whose 1st term is 6.5 and the ratio 5
Calculate the equation of the tangent line ay=sin(x) cos⁡(x)en x=π/2
Log(45)
41/39 - 1/38
A force of 750 pounds compresses a spring 3 inches from its natural length, which is 15 inches. What will be the work done to compress it 3 inches more?
4x/2+5x-3/6=7/8-1/4-x
What is the total tolerance for a dimension from 1.996" to 2.026*?
Prove that it is not possible to arrange the integers 1 to 240 in a table with 15 rows and 16 columns in such a way that the sum of the numbers in each of the columns is the same.
The cost of unleaded gasoline in the Bay Area once followed an unknown distribution with a mean of $4.59 and a standard deviation of $0.10. Sixteen gas stations from the Bay Area are randomly chosen. We are interested in the average cost of gasoline for the 16 gas stations. 84. Find the probability that the average price for 30 gas stations is less than $4.55. a 0.6554 b 0.3446 c 0.0142 d 0.9858 e 0
The simple average of 15 , 30 , 40 , and 45 is
The question is using rule 72 determine Kari wants to save 10,000 for a down payment on a house. Illustrate the difference in years it will take her to double her current 5,000 savings based on 6%, 12% and 18% interest rate .
a survey showed that 3 out of 7 voters would vote in an election. based on this survey, how many people would vote in a city with 25,000 people?
viii. An ac circuit with a 80 μF capacitor in series with a coil of resistance 16Ω and inductance 160mH is connected to a 100V, 100 Hz supply is shown below. Calculate 7. the inductive reactance 8. the capacitive reactance 9. the circuit impedance and V-I phase angle θ 10. the circuit current I 11. the phasor voltages VR, VL, VC and VS 12. the resonance circuit frequency Also construct a fully labeled and appropriately ‘scaled’ voltage phasor diagram.
We plan to test whether the mean mRNA expression level differs between two strains of yeast, for each of 8,000 genes. We will measure the expression levels of each gene, in n samples of strain 1 and m samples of strain 2. We plan to compute a P-value for each gene, using an unpaired two-sample t-test for each gene (the particular type of test does not matter). a) What are the null hypotheses in these tests (in words)? [2] b) If, in fact, the two strains are identical, how many of these tests do we expect to produce a P-value exceeding 1/4? [2]
Find the vertex F(x)=x^2-10x
If sin A=0.3 and cos A=0.6, determine the value of tan A.
64-6x^2>0
Hola👋🏻 Toca en "Crear Nueva Tarea" para enviar tu problema de matemáticas. ¡Uno de nuestros expertos comenzará a trabajar en ello de inmediato!
Write a linear equation in the slope-intercept form. Slope of the line is -1 and goes through (8,4)