Question

A crawler hoe having a 2.5-cy bucket and whose cost per hour, including the wages to an operator, is $109 will excavate and load haul units under the stated conditions as - depth of excavation is 12 feet, angle of swing is 80 degrees, percent swell is 14 and efficiency factor is 55 min per hour. The maximum digging depth of the machine is 22 feet. Use load bucket time 6 sec; swing loaded time 6 sec; dump bucket time 4 sec and swing empty time 5 sec. Determine the cost per bank cubic yard for the material sand and gravel. Show all the calculations with all the required checking.

86

likes
432 views

Answer to a math question A crawler hoe having a 2.5-cy bucket and whose cost per hour, including the wages to an operator, is $109 will excavate and load haul units under the stated conditions as - depth of excavation is 12 feet, angle of swing is 80 degrees, percent swell is 14 and efficiency factor is 55 min per hour. The maximum digging depth of the machine is 22 feet. Use load bucket time 6 sec; swing loaded time 6 sec; dump bucket time 4 sec and swing empty time 5 sec. Determine the cost per bank cubic yard for the material sand and gravel. Show all the calculations with all the required checking.

Expert avatar
Fred
4.4
120 Answers
To calculate the cost per bank cubic yard for the material sand and gravel, we need to consider the following steps:

1. Calculate the bucket capacity in bank cubic yards (BCY):
Given bucket capacity = 2.5 cubic yards
Percent swell = 14%
Bucket capacity in BCY = bucket capacity / (1 + swell/100)
Bucket capacity in BCY = 2.5 / (1 + 14/100) = 2.19 BCY

2. Determine the bank cubic yards per load:
Given depth of excavation = 12 feet
Maximum digging depth of the machine = 22 feet
Bank cubic yards per foot = 1
Bank cubic yards per load = depth of excavation * 2 * bucket capacity in BCY
Bank cubic yards per load = 12 * 2 * 2.19 = 52.56 BCY

3. Calculate the cycle time in minutes:
Given load bucket time = 6 sec
Given swing loaded time = 6 sec
Given dump bucket time = 4 sec
Given swing empty time = 5 sec
Cycle time = (load bucket time + swing loaded time + dump bucket time + swing empty time) / 60
Cycle time = (6 + 6 + 4 + 5) / 60 = 0.2167 hours

4. Determine the production rate in bank cubic yards per hour:
Given efficiency factor = 55% = 0.55
Production rate = 60 / cycle time * efficiency factor
Production rate = 60 / 0.2167 * 0.55 = 151.29 BCY/hr

5. Calculate the operating cost per bank cubic yard:
Given cost per hour = 109Operating cost per bank cubic yard = cost per hour / production rateOperating cost per bank cubic yard = 109 / 151.29 = 0.72 per BCY

### Answer
The cost per bank cubic yard for the material sand and gravel is 0.72$ per BCY.

Frequently asked questions (FAQs)
What is the derivative of the function f(x) = 3x^2 + 4x - 7 with respect to x?
+
What is the value of a constant function when f(x) = c, if c = 5?
+
Math question: What is the formula for finding the volume of a cone?
+
New questions in Mathematics
calculate the derivative by the limit definition: f(x) = 6x^3 + 2
CASE 6-1: PREPARE A PRODUCTION PLAN: WHAT PROBLEMS ARRIVE? Midwest Plastics Company has conducted profit planning for several years. The president stated (with justification) that inventory control and planning had not been satisfactory, which was mainly due to poor planning of production and inventory budgets. Please analyze and provide recommendations, in detail, on the issue regarding the 20B profit plan, which is now being prepared. Their analysis and recommendations will be presented to the executive committee. Despite the seasonality factor, the sales department has been successful in developing a sales plan, on a monthly basis, for each year. The following sales data is available for 20B. 1. Sales plan summary for 20B: 2. Finished goods inventory, as of January 1, 20B, is 96,000 units. 3. Work-in-process inventory will remain constant. 4. Actual annual sales in 20A, including the estimate for December, were 350,000 units. 5. The average finished goods inventory during 20A was 70,000 units. IT IS REQUESTED. 1. Prepare the annual production budget, assuming that management policy is to budget ending finished goods inventory at a standard quantity, based on the ratio of historical sales of 20A to inventory turnover. 2. Prepare a schedule showing sales, production, and inventory levels for each month, assuming: 1) stable inventory, 2) stable production, and 3) recommended inventory-production levels. In developing your recommendations, assume that the following policies have been established: a) The president has set the policy that a maximum inventory of 85,000 units and a minimum inventory of 75,000 units should be used, except in abnormal circumstances. b) A stable level of production is definitely preferred, except that during the holiday season in July and August, production may be reduced by 25 percent. Likewise, a variation in production of 7.5 percent above and below the average level is acceptable. 3. What are the main problems faced by the company in production planning? Make your general recommendations.
8x-(5-x)
calculate the following vector based on its base vectors a= -18i,26j
1/2x +3 <4x-7
2x-y=5 x-y=4
X^2 = 25
3x+5y=11 2x-3y=1
If f(x) = 3x 2, what is the value of x so that f(x) = 11?
4X^2 25
Margin of error E=0.30 populations standard deviation =2.5. Population means with 95% confidence. What I the required sample size (round up to the whole number)
Substitute a=2 and b=-3 and c=-4 to evaluate 2ac/(-2b^2-a)
A person decides to invest money in fixed income securities to redeem it at the end of 3 years. In this way, you make monthly deposits of R$300.00 in the 1st year, R$400.00 in the 2nd year and R$500.00 in the 3rd year. Calculate the amount, knowing that compound interest is 0.6% per month for the entire period. The answer is 15,828.60
Calculate the change in internal energy of a gas that receives 16000 J of heat at constant pressure (1.3 atm) expanding from 0.100 m3 to 0.200 m3. Question 1Answer to. 7050J b. 2125J c. None of the above d. 2828J and. 10295 J
A property sold for $745,000 in a co-brokered transaction. The seller has agreed to pay a 7% commission to the listing firm. The listing firm has agreed to equally split the commission with the selling firm. If the buyer’s broker will receive 8% of the selling firm’s commission, how much commission will the buyer’s broker receive? $14,900 $3725 $$37250 $18625
Let G be the center of gravity of triangle ABC. We draw through A a parallel to BC on which we take a point D so that DGβŠ₯BG. If the area of the quadrilateral AGBD is equal to s, show that ACΒ·BDβ‰₯2Β·s.
Find I (Intrest) using simple interest formula of 17700 @ 15% for 4 years
Identify the slope and y intercept y=11+2/3x
Emile organizes a community dance to raise funds. In addition to paying $300 to rent the room, she must rent chairs at $2 each. The quantity of chairs rented will be equal to the number of tickets sold. She sells tickets for $7 each. How much should she sell to raise money?
I have a complex function I would like to integrate over. I can use two approaches and they should give the same solution. If I want to find the contour integral βˆ«π›Ύπ‘§Β―π‘‘π‘§ for where 𝛾 is the circle |π‘§βˆ’π‘–|=3 oriented counterclockwise I get the following: ∫2πœ‹0𝑖+3π‘’π‘–π‘‘βŽ―βŽ―βŽ―βŽ―βŽ―βŽ―βŽ―βŽ―βŽ―βŽ―βŽ―βŽ―βŽ―βŽ―βŽ―βŽ―βŽ―π‘‘(𝑖+3𝑒𝑖𝑑)=∫2πœ‹03𝑖(βˆ’π‘–+3π‘’βˆ’π‘–π‘‘)𝑒𝑖𝑑𝑑𝑑=18πœ‹π‘– If I directly apply the Residue Theorem, I would get βˆ«π›Ύπ‘§Β―π‘‘π‘§=2πœ‹π‘–Res(𝑓,𝑧=0)=2πœ‹π‘–