Question

A crawler hoe having a 2.5-cy bucket and whose cost per hour, including the wages to an operator, is $109 will excavate and load haul units under the stated conditions as - depth of excavation is 12 feet, angle of swing is 80 degrees, percent swell is 14 and efficiency factor is 55 min per hour. The maximum digging depth of the machine is 22 feet. Use load bucket time 6 sec; swing loaded time 6 sec; dump bucket time 4 sec and swing empty time 5 sec. Determine the cost per bank cubic yard for the material sand and gravel. Show all the calculations with all the required checking.

86

likes
432 views

Answer to a math question A crawler hoe having a 2.5-cy bucket and whose cost per hour, including the wages to an operator, is $109 will excavate and load haul units under the stated conditions as - depth of excavation is 12 feet, angle of swing is 80 degrees, percent swell is 14 and efficiency factor is 55 min per hour. The maximum digging depth of the machine is 22 feet. Use load bucket time 6 sec; swing loaded time 6 sec; dump bucket time 4 sec and swing empty time 5 sec. Determine the cost per bank cubic yard for the material sand and gravel. Show all the calculations with all the required checking.

Expert avatar
Fred
4.4
120 Answers
To calculate the cost per bank cubic yard for the material sand and gravel, we need to consider the following steps:

1. Calculate the bucket capacity in bank cubic yards (BCY):
Given bucket capacity = 2.5 cubic yards
Percent swell = 14%
Bucket capacity in BCY = bucket capacity / (1 + swell/100)
Bucket capacity in BCY = 2.5 / (1 + 14/100) = 2.19 BCY

2. Determine the bank cubic yards per load:
Given depth of excavation = 12 feet
Maximum digging depth of the machine = 22 feet
Bank cubic yards per foot = 1
Bank cubic yards per load = depth of excavation * 2 * bucket capacity in BCY
Bank cubic yards per load = 12 * 2 * 2.19 = 52.56 BCY

3. Calculate the cycle time in minutes:
Given load bucket time = 6 sec
Given swing loaded time = 6 sec
Given dump bucket time = 4 sec
Given swing empty time = 5 sec
Cycle time = (load bucket time + swing loaded time + dump bucket time + swing empty time) / 60
Cycle time = (6 + 6 + 4 + 5) / 60 = 0.2167 hours

4. Determine the production rate in bank cubic yards per hour:
Given efficiency factor = 55% = 0.55
Production rate = 60 / cycle time * efficiency factor
Production rate = 60 / 0.2167 * 0.55 = 151.29 BCY/hr

5. Calculate the operating cost per bank cubic yard:
Given cost per hour = 109Operating cost per bank cubic yard = cost per hour / production rateOperating cost per bank cubic yard = 109 / 151.29 = 0.72 per BCY

### Answer
The cost per bank cubic yard for the material sand and gravel is 0.72$ per BCY.

Frequently asked questions (FAQs)
What is the derivative of the function f(x) = x^3 - 2x^2 + 5x + 1?
+
Find the maximum value of the sine function f(x) = sin x for x in radians between 0 and 2π.
+
"Find the circumference of a circle with radius 8cm."
+
New questions in Mathematics
calculate the derivative by the limit definition: f(x) = 6x^3 + 2
-x+3x-2,si x=3
10! - 8! =
A college believes that 22% of applicants to that school have parents who have remarried. How large a sample is needed to estimate the true proportion of students who have parents who have remarried to within 5 percentage points?
Use the elimination to find the solution to each linear system. X+y=43 2x-y=20
A, B, C and D are numbers; If ABCD = 23, What is the result of ABCD BCDA CDAB DABC operation?
How many different ways can a psychology student select 5 subjects from a pool of 20 subjects and assign each one to a different experiment?
(-5/6)-(-5/4)
solve for x 50x+ 120 (176-x)= 17340
6-35 A recent study by an environmental watchdog determined that the amount of contaminants in Minnesota lakes (in parts per million) it has a normal distribution with a mean of 64 ppm and variance of 17.6. Assume that 35 lakes are randomly selected and sampled. Find the probability that the sample average of the amount of contaminants is a) Greater than 72 ppm. b) Between 64 and 72 ppm. c) Exactly 64 ppm. d) Greater than 94 ppm.
Let A, B, C and D be sets such that | A| = |C| and |B| = |D|. Prove that |A × B| = |C × D|
Convert 9/13 to a percent
Let v be the set of all ordered pairs of real numbers and consider the scalar addition and multiplication operations defined by: u+v=(x,y)+(s,t)=(x+s+1,y+t -two) au=a.(x,y)=(ax+a-1,ay-2a+2) It is known that this set with the operations defined above is a vector space. A) calculate u+v is au for u=(-2,3),v=(1,-2) and a=2 B) show that (0,0) #0 Suggestion find a vector W such that u+w=u C) who is the vector -u D) show that axiom A4 holds:-u+u=0
(2m+3)(4m+3)=0
In a company dedicated to packaging beer in 750 mL containers, a normal distribution is handled in its packaging process, which registers an average of 745 mL and a standard deviation of 8 mL. Determine: a) The probability that a randomly selected container exceeds 765 mL of beer b) The probability that the beer content of a randomly selected container is between 735 and 755 mL.
List five numbers that belong to the 5 (mod 6) numbers. Alternate phrasing, list five numbers that satisfy equation x = 5 (mod 6)
00 piece jigsaw puzzle. the completed puzzle is 10x10. each piech connects to at least 2 other pieces. i plan to assemble by taking pieces out of box one by one. if i've already taken out 2 pieces that dont directly connect, what is the minimum number of additional pieces that i need to draw to in order to guarentee that the original 2 pieces connect?
7- A printing company found in its investigations that there were an average of 6 errors in 150-page prints. Based on this information, what is the probability of there being 48 errors in a 1200-page job?
2+2020202
Triangle ABC has AB=AC and angle BAC =X, with X being less than 60 degrees. Point D lies on AB such that CB = CD Point E lies on AC such that CE= DE Determine angle DEC in terms of X