To calculate the cost per bank cubic yard for the material sand and gravel, we need to consider the following steps:
1. Calculate the bucket capacity in bank cubic yards (BCY):
Given bucket capacity = 2.5 cubic yards
Percent swell = 14%
Bucket capacity in BCY = bucket capacity / (1 + swell/100)
Bucket capacity in BCY = 2.5 / (1 + 14/100) = 2.19 BCY
2. Determine the bank cubic yards per load:
Given depth of excavation = 12 feet
Maximum digging depth of the machine = 22 feet
Bank cubic yards per foot = 1
Bank cubic yards per load = depth of excavation * 2 * bucket capacity in BCY
Bank cubic yards per load = 12 * 2 * 2.19 = 52.56 BCY
3. Calculate the cycle time in minutes:
Given load bucket time = 6 sec
Given swing loaded time = 6 sec
Given dump bucket time = 4 sec
Given swing empty time = 5 sec
Cycle time = (load bucket time + swing loaded time + dump bucket time + swing empty time) / 60
Cycle time = (6 + 6 + 4 + 5) / 60 = 0.2167 hours
4. Determine the production rate in bank cubic yards per hour:
Given efficiency factor = 55% = 0.55
Production rate = 60 / cycle time * efficiency factor
Production rate = 60 / 0.2167 * 0.55 = 151.29 BCY/hr
5. Calculate the operating cost per bank cubic yard:
Given cost per hour = 109Operating cost per bank cubic yard = cost per hour / production rateOperating cost per bank cubic yard = 109 / 151.29 = 0.72 per BCY
### Answer
The cost per bank cubic yard for the material sand and gravel is 0.72$ per BCY.