Question

A crawler hoe having a 2.5-cy bucket and whose cost per hour, including the wages to an operator, is $109 will excavate and load haul units under the stated conditions as - depth of excavation is 12 feet, angle of swing is 80 degrees, percent swell is 14 and efficiency factor is 55 min per hour. The maximum digging depth of the machine is 22 feet. Use load bucket time 6 sec; swing loaded time 6 sec; dump bucket time 4 sec and swing empty time 5 sec. Determine the cost per bank cubic yard for the material sand and gravel. Show all the calculations with all the required checking.

86

likes
432 views

Answer to a math question A crawler hoe having a 2.5-cy bucket and whose cost per hour, including the wages to an operator, is $109 will excavate and load haul units under the stated conditions as - depth of excavation is 12 feet, angle of swing is 80 degrees, percent swell is 14 and efficiency factor is 55 min per hour. The maximum digging depth of the machine is 22 feet. Use load bucket time 6 sec; swing loaded time 6 sec; dump bucket time 4 sec and swing empty time 5 sec. Determine the cost per bank cubic yard for the material sand and gravel. Show all the calculations with all the required checking.

Expert avatar
Fred
4.4
120 Answers
To calculate the cost per bank cubic yard for the material sand and gravel, we need to consider the following steps:

1. Calculate the bucket capacity in bank cubic yards (BCY):
Given bucket capacity = 2.5 cubic yards
Percent swell = 14%
Bucket capacity in BCY = bucket capacity / (1 + swell/100)
Bucket capacity in BCY = 2.5 / (1 + 14/100) = 2.19 BCY

2. Determine the bank cubic yards per load:
Given depth of excavation = 12 feet
Maximum digging depth of the machine = 22 feet
Bank cubic yards per foot = 1
Bank cubic yards per load = depth of excavation * 2 * bucket capacity in BCY
Bank cubic yards per load = 12 * 2 * 2.19 = 52.56 BCY

3. Calculate the cycle time in minutes:
Given load bucket time = 6 sec
Given swing loaded time = 6 sec
Given dump bucket time = 4 sec
Given swing empty time = 5 sec
Cycle time = (load bucket time + swing loaded time + dump bucket time + swing empty time) / 60
Cycle time = (6 + 6 + 4 + 5) / 60 = 0.2167 hours

4. Determine the production rate in bank cubic yards per hour:
Given efficiency factor = 55% = 0.55
Production rate = 60 / cycle time * efficiency factor
Production rate = 60 / 0.2167 * 0.55 = 151.29 BCY/hr

5. Calculate the operating cost per bank cubic yard:
Given cost per hour = 109Operating cost per bank cubic yard = cost per hour / production rateOperating cost per bank cubic yard = 109 / 151.29 = 0.72 per BCY

### Answer
The cost per bank cubic yard for the material sand and gravel is 0.72$ per BCY.

Frequently asked questions (FAQs)
Question: In a right triangle, one leg measures 12 units and the hypotenuse measures 20 units. Find the length of the other leg.
+
Math question: What is the probability of rolling a 3 on a fair six-sided die?
+
What is the square root of 75?
+
New questions in Mathematics
calculate the derivative by the limit definition: f(x) = 6x^3 + 2
10! - 8! =
8x-(5-x)
7273736363-8
1. Suppose we have a good whose quantity supplied changed from 100 to 120 units when the price increased from $10 to $12 per unit. Compute the price elasticity of supply using the midpoint method
An integer is taken at random from the first 40 positive integers. What is the probability that the integer is divisible by 5 or 6?
-0.15/32.6
Solve this mathematical problem if 3/5 of a roll of tape measures 2m. How long is the complete roll?
Emma is on a 50 m high bridge and sees two boats anchored below. From her position, boat A has a bearing of 230° and boat B has a bearing of 120°. Emma estimates the angles of depression to be about 38° for boat A and 35° for boat B. How far apart are the boats to the nearest meter?
4x + 8y = 5 2x + 4y = 10
In the telephone exchange of a certain university, calls come in at a rate of 5 every 2 minutes. Assuming a Poisson distribution, the average number of calls per second is: a) 1/8 b) 1/12 c) 1/10 d) 2/5 e) 1/24
A storage maker price is $2.50 per square feet. Find the price of a custom shed 4 yards long, and 5yards wide and 8 feet tall
P(Z<z)=0.1003
A function is considered exponential when it has a base with positive values greater than zero and different from one, where the exponent is an unknown. An important characteristic of exponential functions is that they show rapid growth or decay as an independent variable increases or decreases. Given the function 25^(x+3)=125, it is calculated that x has the value of
9 x² + 2x + 1 = 0
Show work on 4108 divided by 4
For what values of m is point P (m, 1 - 2m) in the 2⁰ quadrant?
How many cards do you expect to pull from a poker deck until you get an ACE?
Gender and communication : Answer the question ( 1 paragraph is ok) . Please can you write about women? Compared to your other identities, how much of a role does gender play in your life? And has your own sex/gender offered you privileges or disadvantages? How so?
Let I be an interval and let f : I → R be a continuous function such that f(I) ⊂ Q. Show (in symbols) that f is constant.