Question

For each of the following processes, determine whether in CPM or PERT: (1) Prepare a Network Diagram, (2) Determine the Different Routes and Indicate which is the Critical Path (3) Determine the Early and Late Start and End Times of each activity. (4) Determine the Slack of each Activity (5) Prepare a Gantt Chart (6) Indicate the Variance and Standard Deviation of the projects (7) Estimate the probability of meeting the desired times or the time for the desired probability Exercise 6 Probability 97% Activity Predecessor amb A - 1 1 1 BA 2 3 10 CB 2.5 3.5 5 DC 4 5 6 EC 2 2 2 FB 5 6 9 GG 1 7 9 HE, G 7 8 9 ID 2 3 4 JI 1 1.5 2 KH,J 2 2 2 LK 1 5 9 ML 7 8 9

103

likes
517 views

Answer to a math question For each of the following processes, determine whether in CPM or PERT: (1) Prepare a Network Diagram, (2) Determine the Different Routes and Indicate which is the Critical Path (3) Determine the Early and Late Start and End Times of each activity. (4) Determine the Slack of each Activity (5) Prepare a Gantt Chart (6) Indicate the Variance and Standard Deviation of the projects (7) Estimate the probability of meeting the desired times or the time for the desired probability Exercise 6 Probability 97% Activity Predecessor amb A - 1 1 1 BA 2 3 10 CB 2.5 3.5 5 DC 4 5 6 EC 2 2 2 FB 5 6 9 GG 1 7 9 HE, G 7 8 9 ID 2 3 4 JI 1 1.5 2 KH,J 2 2 2 LK 1 5 9 ML 7 8 9

Expert avatar
Adonis
4.4
106 Answers
To determine whether each process belongs to CPM or PERT:

(1) Prepare a Network Diagram: This process belongs to PERT as it involves probabilistic time estimates for activities.

(2) Determine the Different Routes and Indicate which is the Critical Path: This process belongs to CPM as it focuses on identifying the critical path based on deterministic time estimates.

(3) Determine the Early and Late Start and End Times of each activity: This process belongs to CPM as it involves calculating early start, late start, early end, and late end times based on deterministic estimates.

(4) Determine the Slack of each Activity: This process belongs to CPM as it calculates slack for each activity based on deterministic estimates.

(5) Prepare a Gantt Chart: This process belongs to CPM as it is used for scheduling and visualizing project tasks based on deterministic estimates.

(6) Indicate the Variance and Standard Deviation of the projects: This process belongs to PERT as it involves calculating variance and standard deviation for project completion time based on probabilistic estimates.

(7) Estimate the probability of meeting the desired times or the time for the desired probability: This process belongs to PERT as it uses probabilistic estimates to determine the probability of meeting project completion times.

Answer: All the processes except (6) Indicate the Variance and Standard Deviation of the projects belong to CPM.

Frequently asked questions (FAQs)
What is the equation of an ellipse with center (2, -3), major axis length 10, and minor axis length 8?
+
What is the 4th derivative of the function f(x) = sin(x^2)?
+
Question: What is the basic shape of the graph of a quadratic function?
+
New questions in Mathematics
a to the power of 2 minus 16 over a plus 4, what is the result?
Solution of the equation y'' - y' -6y = 0
Let the vectors be u=(-1,0,2) , v=(0,2,-3) , w=(2,2,3) Calculate the following expressions a)<u,w> b) &lt;2u- 5v,3w&gt;
What payment 7 months from now would be equivalent in value to a $3,300 payment due 23 months from now? The value of money is 2.7% simple interest. Round your answer to 2 decimal places. Show all work and how you arrive at the answer..
Substitute a=2 and b=-3 and c=-4 to evaluate 2ac/(-2b^2-a)
The average number of babies born at a hospital is 6 per hour. What is the probability that three babies are born during a particular 1 hour period?
A triangular window has a base of 6 ft. and a height of 7 ft. What is its area?
Given (3x+2)E [2;14] how much money (in soles) does Sophia have if numerically it is the greatest value of x?
sum of 7a-4b+5c, -7a+4b-6c
The question is using rule 72 determine Kari wants to save 10,000 for a down payment on a house. Illustrate the difference in years it will take her to double her current 5,000 savings based on 6%, 12% and 18% interest rate .
A Smooth Plane is listed for $195.00. Discounts of 12% and 10% are allowed. If the customer pays cash within 30 days, an additional discount of 3% is granted. What is the cost if a carpenter takes advantage of all the discounts offered?
Let f and g be defined in R and suppose that there exists M > 0 such that |f(x) − f(p)| ≤ M|g(x) − g(p)|, for all x. Prove that if g is continuous in p, then f will also be continuous in p.
1. A jeweler has two gold bars, with 80% purity and the other with 95% purity. How much of each must be melted to obtain a 5 kilo ingot with 86% purity?
Log0
For the numbers below, select a number at random and find the probability that: a. The number is even b. The sum of the number’s digit is even c. The number is greater than 50 2 3 5 7 11 13 17 19 23 29 31 37 41 43 47 53 59 61 67 71 73 79 83 89 97
x²-7x+12=0
A candy manufacturer must monitor deviations in the amount of sugar in their products They want their products to meet standards. They selected a random sample of 20 candies and found that the sandard deviation of that sample is 1.7. What is the probabilty of finding a sample variance as high or higher if the population variance is actually 3277 Assume the population distribution is normal.
7-1=6 6x2=12 Explain that
What is the set-off agreement? Make your own example, describe and put in T accounts how you record transactions.
5 1/9 + 2 2/3