Question

For each of the following processes, determine whether in CPM or PERT: (1) Prepare a Network Diagram, (2) Determine the Different Routes and Indicate which is the Critical Path (3) Determine the Early and Late Start and End Times of each activity. (4) Determine the Slack of each Activity (5) Prepare a Gantt Chart (6) Indicate the Variance and Standard Deviation of the projects (7) Estimate the probability of meeting the desired times or the time for the desired probability Exercise 6 Probability 97% Activity Predecessor amb A - 1 1 1 BA 2 3 10 CB 2.5 3.5 5 DC 4 5 6 EC 2 2 2 FB 5 6 9 GG 1 7 9 HE, G 7 8 9 ID 2 3 4 JI 1 1.5 2 KH,J 2 2 2 LK 1 5 9 ML 7 8 9

103

likes
517 views

Answer to a math question For each of the following processes, determine whether in CPM or PERT: (1) Prepare a Network Diagram, (2) Determine the Different Routes and Indicate which is the Critical Path (3) Determine the Early and Late Start and End Times of each activity. (4) Determine the Slack of each Activity (5) Prepare a Gantt Chart (6) Indicate the Variance and Standard Deviation of the projects (7) Estimate the probability of meeting the desired times or the time for the desired probability Exercise 6 Probability 97% Activity Predecessor amb A - 1 1 1 BA 2 3 10 CB 2.5 3.5 5 DC 4 5 6 EC 2 2 2 FB 5 6 9 GG 1 7 9 HE, G 7 8 9 ID 2 3 4 JI 1 1.5 2 KH,J 2 2 2 LK 1 5 9 ML 7 8 9

Expert avatar
Adonis
4.4
105 Answers
To determine whether each process belongs to CPM or PERT:

(1) Prepare a Network Diagram: This process belongs to PERT as it involves probabilistic time estimates for activities.

(2) Determine the Different Routes and Indicate which is the Critical Path: This process belongs to CPM as it focuses on identifying the critical path based on deterministic time estimates.

(3) Determine the Early and Late Start and End Times of each activity: This process belongs to CPM as it involves calculating early start, late start, early end, and late end times based on deterministic estimates.

(4) Determine the Slack of each Activity: This process belongs to CPM as it calculates slack for each activity based on deterministic estimates.

(5) Prepare a Gantt Chart: This process belongs to CPM as it is used for scheduling and visualizing project tasks based on deterministic estimates.

(6) Indicate the Variance and Standard Deviation of the projects: This process belongs to PERT as it involves calculating variance and standard deviation for project completion time based on probabilistic estimates.

(7) Estimate the probability of meeting the desired times or the time for the desired probability: This process belongs to PERT as it uses probabilistic estimates to determine the probability of meeting project completion times.

Answer: All the processes except (6) Indicate the Variance and Standard Deviation of the projects belong to CPM.

Frequently asked questions (FAQs)
What is the result of adding vector A (magnitude 3, direction 30 degrees) to vector B (magnitude 4, direction 120 degrees)?
+
The math question is: Find the limit as x approaches 5 of (3x - 9)/(x^2 - 25).
+
What is the derivative of y = cos(3x) - 2sin(2x) + tan(4x) - cot(5x)?
+
New questions in Mathematics
A particular employee arrives at work sometime between 8:00 a.m. and 8:40 a.m. Based on past experience the company has determined that the employee is equally likely to arrive at any time between 8:00 a.m. and 8:40 a.m. Find the probability that the employee will arrive between 8:05 a.m. and 8:30 a.m. Round your answer to four decimal places, if necessary.
Since one of the three integers whose product is (-60) is (+4), write the values that two integers can take.
Use the digits of 1,9,2,3 to come up with all the numbers 98 and 95
Reparameterize the curve r(t)= cos(t)i without (t)j (t)k by the arc length.
How many anagrams of the word STROMEC there that do not contain STROM, MOST, MOC or CEST as a subword? By subword is meant anything that is created by omitting some letters - for example, the word EMROSCT contains both MOC and MOST as subwords.
Suppose the Golf ball market is perfectly competitive and the functions are known: Q = 120 – 2Px – 2Py 0.2I Q = 2Px 40 Where I = Consumers' income ($200) and Py = Price of Good Y (40) Calculate the equilibrium elasticity: a) 1.6 b) -6 c) 6 d) 0.6
A study reports the following final notation: F (3, 32) = 9.50, p < .05. How many total participants were involved in this study? Group of answer choices 34 32 36
Calculate the minimum size of a simple random sample assuming a sampling error of 5% assuming that the population size is 100 elements
Engineers want to design seats in commercial aircraft so that they are wide enough to fit ​95% of all males.​ (Accommodating 100% of males would require very wide seats that would be much too​ expensive.) Men have hip breadths that are normally distributed with a mean of 14.4 in. and a standard deviation of 1.2 in. Find P95. That​ is, find the hip breadth for men that separates the smallest ​95% from the largest 5​%.
The probability of growing a seedling from a seed is 0.62. How many seeds do I need to plant so that the probability of growing at least one seedling is greater than or equal to 0.87?
Take the limit of (sin(x-4))/(tan(x^2 - 16) as x approaches 4.
Translate to an equation and solve. Let x be the unknown number: What number is 52% of 81.
Find sup { x∈R, x²+3<4x }. Justify the answer
Log0
P 13. Let P a point inside of a square ABCD. Show that the perpendicular lines drawn from A, B, C, respectively D, to BP, CP, DP, respectively AP are concurrent. Use geometric rotation.
A group of 17 people spent 9 days on vacation and spent R$776.34 on barbecue meat and the bill needs to be divided as follows: 6 people stayed for 9 days, 7 people stayed for 4 days, and 2 people stayed for 5 days and 2 people stayed 3 days, how much does each group have to pay for the days they stayed?
4m - 3t + 7 = 16
Emile organizes a community dance to raise funds. In addition to paying $300 to rent the room, she must rent chairs at $2 each. The quantity of chairs rented will be equal to the number of tickets sold. She sells tickets for $7 each. How much should she sell to raise money?
The following incoming payments show up at a tax inspection: 25 000€ on 19.01.2008, 140 000€ on 27.03.2008 and 19 000€ on a date that which is illegible, and 60 000€ on 15.06.2008. On which date did the payment of the 19 000€ appear, if on 30.06.2008 the money on the account (incl. interest at 4%) is 246 088.89€? Use simple interest and 30E/360 DCC. Solution: 45 days, 15.05.08
Sin(5pi/3)