Question

For each of the following processes, determine whether in CPM or PERT: (1) Prepare a Network Diagram, (2) Determine the Different Routes and Indicate which is the Critical Path (3) Determine the Early and Late Start and End Times of each activity. (4) Determine the Slack of each Activity (5) Prepare a Gantt Chart (6) Indicate the Variance and Standard Deviation of the projects (7) Estimate the probability of meeting the desired times or the time for the desired probability Exercise 6 Probability 97% Activity Predecessor amb A - 1 1 1 BA 2 3 10 CB 2.5 3.5 5 DC 4 5 6 EC 2 2 2 FB 5 6 9 GG 1 7 9 HE, G 7 8 9 ID 2 3 4 JI 1 1.5 2 KH,J 2 2 2 LK 1 5 9 ML 7 8 9

103

likes
517 views

Answer to a math question For each of the following processes, determine whether in CPM or PERT: (1) Prepare a Network Diagram, (2) Determine the Different Routes and Indicate which is the Critical Path (3) Determine the Early and Late Start and End Times of each activity. (4) Determine the Slack of each Activity (5) Prepare a Gantt Chart (6) Indicate the Variance and Standard Deviation of the projects (7) Estimate the probability of meeting the desired times or the time for the desired probability Exercise 6 Probability 97% Activity Predecessor amb A - 1 1 1 BA 2 3 10 CB 2.5 3.5 5 DC 4 5 6 EC 2 2 2 FB 5 6 9 GG 1 7 9 HE, G 7 8 9 ID 2 3 4 JI 1 1.5 2 KH,J 2 2 2 LK 1 5 9 ML 7 8 9

Expert avatar
Adonis
4.4
102 Answers
To determine whether each process belongs to CPM or PERT:

(1) Prepare a Network Diagram: This process belongs to PERT as it involves probabilistic time estimates for activities.

(2) Determine the Different Routes and Indicate which is the Critical Path: This process belongs to CPM as it focuses on identifying the critical path based on deterministic time estimates.

(3) Determine the Early and Late Start and End Times of each activity: This process belongs to CPM as it involves calculating early start, late start, early end, and late end times based on deterministic estimates.

(4) Determine the Slack of each Activity: This process belongs to CPM as it calculates slack for each activity based on deterministic estimates.

(5) Prepare a Gantt Chart: This process belongs to CPM as it is used for scheduling and visualizing project tasks based on deterministic estimates.

(6) Indicate the Variance and Standard Deviation of the projects: This process belongs to PERT as it involves calculating variance and standard deviation for project completion time based on probabilistic estimates.

(7) Estimate the probability of meeting the desired times or the time for the desired probability: This process belongs to PERT as it uses probabilistic estimates to determine the probability of meeting project completion times.

Answer: All the processes except (6) Indicate the Variance and Standard Deviation of the projects belong to CPM.

Frequently asked questions (FAQs)
Question: Find the value of sin(2θ) - cos(θ) when θ = π/4.
+
Math question: In △ABC and △DEF, if AB = DE, BC = EF, and ∠ACB = ∠DFE, what can we conclude about the triangles?
+
What is the measure of the angle formed by an angle bisector if one of the angles is 75 degrees?
+
New questions in Mathematics
10! - 8! =
A drawer contains three pairs of white socks, five pairs of black socks and two pairs of red socks. Caden randomly selects two pairs of socks on his way to the gym. What is the probability that both pairs of socks are black?
224 × (6÷8)
Divide 22 by 5 solve it by array and an area model
how many arrangements can be made of 4 letters chosen from the letters of the world ABSOLUTE in which the S and U appear together
Solve this mathematical problem if 3/5 of a roll of tape measures 2m. How long is the complete roll?
A construction company is working on two projects: house construction and building construction. Each house requires 4 weeks of work and produces a profit of $50,000. Each building requires 8 weeks of work and produces a profit of $100,000. The company has a total of 24 work weeks available. Furthermore, it is known that at least 2 houses and at least 1 building must be built to meet the demand. The company wants to maximize its profits and needs to determine how many houses and buildings it should build to meet demand and maximize profits, given time and demand constraints.
5.- From the probabilities: 𝐏(𝐁) = 𝟑𝟎% 𝐏(𝐀 ∩ 𝐁) = 𝟐𝟎% 𝐏(𝐀 ̅) = 𝟕𝟎% You are asked to calculate: 𝐏(𝐀 ∪ 𝐁)
solve for x 50x+ 120 (176-x)= 17340
What is 28 marks out of 56 as a percentage
A circular window has a rubber molding around the edge. If the window has a radius of 250 mm, how long is the piece of molding that is required ? (To the nearest mm)
Exercise 1 An ejidal association wishes to determine the distribution for the three different crops that it can plant for the next season on its available 900 hectares. Information on the total available and how many resources are required for each hectare of cultivation is shown in the following tables: Total available resource Water 15,000 m3 Fertilizer 5,000 kg Labor 125 day laborers Requirements per cultivated hectare Corn Soybeans Wheat Water 15 25 20 Fertilizer 5 8 7 Labor** 1/8 1/5 1/4 *The data in fraction means that with one day laborer it will be possible to care for 8, 5 and 4 hectares respectively. * Sales of crops 1 and 3, according to information from the Department of Agriculture, are guaranteed and exceed the capacity of the cooperative. However, soybeans must be limited to a maximum of 150 hectares. On the other hand, the profits for each hectare of crop obtained are estimated at: $7,500 for corn, $8,500 for soybeans and $8,000 for wheat. The objectives are to determine: • How many hectares of each crop must be allocated so that the profit is maximum. R= • The estimated profits for the ejidal cooperative in the next growing season. R=
A company receives sales in $20 per book and $18 per calculator. The per unit cost to manufacture each book and calculator are $5 and 4$ respectively. The monthly (30 day) cost must not exceed $27000 per month. If the manufacturing equipment used by the company takes five minutes to produce a book and 15 minutes to produce a calculator, how many books and calculators should the company produce to maximise profit? Please solve graphically and
From 1975 through 2020 the mean annual gain of the Dow Jones Industrial Average was 652. A random sample of 34 years is selected from this population. What is the probability that the mean gain for the sample was between 400 and 800? Assume the standard deviation is 1539
The question is using rule 72 determine Kari wants to save 10,000 for a down payment on a house. Illustrate the difference in years it will take her to double her current 5,000 savings based on 6%, 12% and 18% interest rate .
392929-9
Solve the following 9x - 9 - 6x = 5 + 8x - 9
-6 - t / 4 = -1
Find the orthogonal projection of a point A = (1, 2, -1) onto a line passing through the points Pi = (0, 1, 1) and P2 = (1, 2, 3).
8(x+4) -4=4x-1