Question

For each of the following processes, determine whether in CPM or PERT: (1) Prepare a Network Diagram, (2) Determine the Different Routes and Indicate which is the Critical Path (3) Determine the Early and Late Start and End Times of each activity. (4) Determine the Slack of each Activity (5) Prepare a Gantt Chart (6) Indicate the Variance and Standard Deviation of the projects (7) Estimate the probability of meeting the desired times or the time for the desired probability Exercise 6 Probability 97% Activity Predecessor amb A - 1 1 1 BA 2 3 10 CB 2.5 3.5 5 DC 4 5 6 EC 2 2 2 FB 5 6 9 GG 1 7 9 HE, G 7 8 9 ID 2 3 4 JI 1 1.5 2 KH,J 2 2 2 LK 1 5 9 ML 7 8 9

103

likes
517 views

Answer to a math question For each of the following processes, determine whether in CPM or PERT: (1) Prepare a Network Diagram, (2) Determine the Different Routes and Indicate which is the Critical Path (3) Determine the Early and Late Start and End Times of each activity. (4) Determine the Slack of each Activity (5) Prepare a Gantt Chart (6) Indicate the Variance and Standard Deviation of the projects (7) Estimate the probability of meeting the desired times or the time for the desired probability Exercise 6 Probability 97% Activity Predecessor amb A - 1 1 1 BA 2 3 10 CB 2.5 3.5 5 DC 4 5 6 EC 2 2 2 FB 5 6 9 GG 1 7 9 HE, G 7 8 9 ID 2 3 4 JI 1 1.5 2 KH,J 2 2 2 LK 1 5 9 ML 7 8 9

Expert avatar
Adonis
4.4
105 Answers
To determine whether each process belongs to CPM or PERT:

(1) Prepare a Network Diagram: This process belongs to PERT as it involves probabilistic time estimates for activities.

(2) Determine the Different Routes and Indicate which is the Critical Path: This process belongs to CPM as it focuses on identifying the critical path based on deterministic time estimates.

(3) Determine the Early and Late Start and End Times of each activity: This process belongs to CPM as it involves calculating early start, late start, early end, and late end times based on deterministic estimates.

(4) Determine the Slack of each Activity: This process belongs to CPM as it calculates slack for each activity based on deterministic estimates.

(5) Prepare a Gantt Chart: This process belongs to CPM as it is used for scheduling and visualizing project tasks based on deterministic estimates.

(6) Indicate the Variance and Standard Deviation of the projects: This process belongs to PERT as it involves calculating variance and standard deviation for project completion time based on probabilistic estimates.

(7) Estimate the probability of meeting the desired times or the time for the desired probability: This process belongs to PERT as it uses probabilistic estimates to determine the probability of meeting project completion times.

Answer: All the processes except (6) Indicate the Variance and Standard Deviation of the projects belong to CPM.

Frequently asked questions (FAQs)
What is the unit vector in the direction of vector v = (4, -3) in ℝ^2?
+
What is the y-intercept of the function f(x) = 1/x?
+
Math Question: Find the absolute extrema of the function f(x) = x^2 - 4x + 3 on the interval [0, 5].
+
New questions in Mathematics
A normal random variable x has a mean of 50 and a standard deviation of 10. Would it be unusual to see the value x = 0? Explain your answer.
1 + 1
Using a remarkable product you must factor the expression: f(x) =36x^2-324 and you are entitled to 5 steps
the value of sin 178°58'
what is 9% of 307
In a store there are packets of chocolate, strawberry, tutti-frutti, lemon, grape and banana sweets. If a person needs to choose 4 flavors of candy from those available, how many ways can they make that choice?
4x567
How many different ways can a psychology student select 5 subjects from a pool of 20 subjects and assign each one to a different experiment?
What is the appropriate measurement for the weight of an African elephant?
find x in the equation 2x-4=6
Exercise 1 An ejidal association wishes to determine the distribution for the three different crops that it can plant for the next season on its available 900 hectares. Information on the total available and how many resources are required for each hectare of cultivation is shown in the following tables: Total available resource Water 15,000 m3 Fertilizer 5,000 kg Labor 125 day laborers Requirements per cultivated hectare Corn Soybeans Wheat Water 15 25 20 Fertilizer 5 8 7 Labor** 1/8 1/5 1/4 *The data in fraction means that with one day laborer it will be possible to care for 8, 5 and 4 hectares respectively. * Sales of crops 1 and 3, according to information from the Department of Agriculture, are guaranteed and exceed the capacity of the cooperative. However, soybeans must be limited to a maximum of 150 hectares. On the other hand, the profits for each hectare of crop obtained are estimated at: $7,500 for corn, $8,500 for soybeans and $8,000 for wheat. The objectives are to determine: • How many hectares of each crop must be allocated so that the profit is maximum. R= • The estimated profits for the ejidal cooperative in the next growing season. R=
A stunt man jumps horizontally from a building to the roof of a garage that is 2 meters lower. How fast does he need to be to land on the roof of the said garage that is 3 meters away from the building?
Next%C3%B3n%2C+we+are+given+a+series+of+Tri%C3%A1angles+Right%C3%A1angles+%3Cbr%2F%3Ey+in+each+one+of+them+ are+known+2%28two%29+measurements+of+sides.+%3Cbr%2F%3Elet's+determine+all+trigonom%C3%A9tric+ratios.
(X+2)(x+3)=4x+18
Let f and g be defined in R and suppose that there exists M > 0 such that |f(x) − f(p)| ≤ M|g(x) − g(p)|, for all x. Prove that if g is continuous in p, then f will also be continuous in p.
Which statement best describes the key changes in perspectives on inclusion? An inclusive program must consider the unique experiences of every child and family as well as the child's strengths and needs. There is a shift in thinking about individual programs as "inclusive programs" to thinking about inclusion as something that reflects the cultural influence of the family. There is a greater emphasis on barriers to full participation and the acknowledgement that all children are unique and must be fully and meaningfully engaged in a program. In an inclusive program all participants are accepted by their peers and other members of the community.
In a 24 hours period, the average number of boats arriving at a port is 10. Assuming that boats arrive at a random rate that is the same for all subintervals of equal length (i.e. the probability of a boat arriving during a 1 hour period the same for every 1 hour period no matter what). Calculate the probability that more than 1 boat will arrive during a 1 hour period. (P(X>1) ) Give your answers to 4 decimal places and in a range between 0 and 1
Pablo has a balance of $440,000 and 2/5 of the money is used to pay bills. How much money do you have left after paying the bills?
solve R the following equation 4 x squared - 35 - 9 over x squared is equal to 0
13/25+7/16