Question

For each of the following processes, determine whether in CPM or PERT: (1) Prepare a Network Diagram, (2) Determine the Different Routes and Indicate which is the Critical Path (3) Determine the Early and Late Start and End Times of each activity. (4) Determine the Slack of each Activity (5) Prepare a Gantt Chart (6) Indicate the Variance and Standard Deviation of the projects (7) Estimate the probability of meeting the desired times or the time for the desired probability Exercise 6 Probability 97% Activity Predecessor amb A - 1 1 1 BA 2 3 10 CB 2.5 3.5 5 DC 4 5 6 EC 2 2 2 FB 5 6 9 GG 1 7 9 HE, G 7 8 9 ID 2 3 4 JI 1 1.5 2 KH,J 2 2 2 LK 1 5 9 ML 7 8 9

103

likes
517 views

Answer to a math question For each of the following processes, determine whether in CPM or PERT: (1) Prepare a Network Diagram, (2) Determine the Different Routes and Indicate which is the Critical Path (3) Determine the Early and Late Start and End Times of each activity. (4) Determine the Slack of each Activity (5) Prepare a Gantt Chart (6) Indicate the Variance and Standard Deviation of the projects (7) Estimate the probability of meeting the desired times or the time for the desired probability Exercise 6 Probability 97% Activity Predecessor amb A - 1 1 1 BA 2 3 10 CB 2.5 3.5 5 DC 4 5 6 EC 2 2 2 FB 5 6 9 GG 1 7 9 HE, G 7 8 9 ID 2 3 4 JI 1 1.5 2 KH,J 2 2 2 LK 1 5 9 ML 7 8 9

Expert avatar
Adonis
4.4
106 Answers
To determine whether each process belongs to CPM or PERT:

(1) Prepare a Network Diagram: This process belongs to PERT as it involves probabilistic time estimates for activities.

(2) Determine the Different Routes and Indicate which is the Critical Path: This process belongs to CPM as it focuses on identifying the critical path based on deterministic time estimates.

(3) Determine the Early and Late Start and End Times of each activity: This process belongs to CPM as it involves calculating early start, late start, early end, and late end times based on deterministic estimates.

(4) Determine the Slack of each Activity: This process belongs to CPM as it calculates slack for each activity based on deterministic estimates.

(5) Prepare a Gantt Chart: This process belongs to CPM as it is used for scheduling and visualizing project tasks based on deterministic estimates.

(6) Indicate the Variance and Standard Deviation of the projects: This process belongs to PERT as it involves calculating variance and standard deviation for project completion time based on probabilistic estimates.

(7) Estimate the probability of meeting the desired times or the time for the desired probability: This process belongs to PERT as it uses probabilistic estimates to determine the probability of meeting project completion times.

Answer: All the processes except (6) Indicate the Variance and Standard Deviation of the projects belong to CPM.

Frequently asked questions (FAQs)
Math question: Find the limit as x approaches 2 of (x^2-4)/(x^3-8) using L'HΓ΄pital's Rule.
+
What is the limit of (7y^2 - 3y + 4)/(4y^2 + y - 2) as y approaches 2?
+
What is the measure in degrees of an angle that is Ο€/6 radians?
+
New questions in Mathematics
a to the power of 2 minus 16 over a plus 4, what is the result?
calculate the following vector based on its base vectors a= -18i,26j
A brass cube with an edge of 3 cm at 40 Β°C increased its volume to 27.12 cm3. What is the final temperature that achieves this increase?
The bus one way of the road which is 10km is heading with speed of 20km/h ,then the bus the other 10km is heading with speed of 60km/h. The middle speed of the road is it equal with arithmetic speed of the v1 and v2 ?
A bird randomly chooses to land on 1 of 12 perches available in its aviary. Determine the Probability of it landing on a perch numbered 8 and then on a perch marked with a prime number; take into account that he never lands on the same perch in the sequence.
9b^2-6b-5
In a store, a person carries 14 kilos of rice and 28 kilos of flour. In what ratio are the kilos found? (Remember to simplify until you reach an irreducible fraction)
Let f(x) = xΒ² βˆ’ 1. Find the equation of the tangent line to the graph of f at the point x0 = 2.
The sum of two numbers is equal to 58 and the largest exceeds by at least 12. Find the two numbers
solve for x 50x+ 120 (176-x)= 17340
Determine the reduced equation of the straight line that is perpendicular to the straight line r: y=4x-10 and passes through the origin of the Cartesian plane
The thermal representation f(x) = 20 times 0.8 to the power of x is known from an exponential function f. Specify the intersection point with the y-axis
The physician orders 15mg of tramadol(liquid). On hand is 30mg/2mL vials. How many mL will the MA administer?
1. A pediatric client is prescribed digoxin for congestive heart failure. The dose prescribed is 40 mcg/kg twice daily. The child weighs 33 pounds. What is the dosage in mg to be given per dose? Round to the nearest hundredth. Calculate your answer in mg per dose. Enter numerical value only.____mg
The simple average of 15 , 30 , 40 , and 45 is
Calculate the difference between 407 and 27
Find the number of pounds of nails required for 17850 square feet of drywall if each thousand square feet requires 4.5 pounds of nails.
effectiveness of fiscal and monetary policy under closed and open economies
f(r) = 1/r+9 find f(x^2) + 1
f(x)= 9-x^2 find (f(x+h)-f(x) )/h