Question

For each of the following processes, determine whether in CPM or PERT: (1) Prepare a Network Diagram, (2) Determine the Different Routes and Indicate which is the Critical Path (3) Determine the Early and Late Start and End Times of each activity. (4) Determine the Slack of each Activity (5) Prepare a Gantt Chart (6) Indicate the Variance and Standard Deviation of the projects (7) Estimate the probability of meeting the desired times or the time for the desired probability Exercise 6 Probability 97% Activity Predecessor amb A - 1 1 1 BA 2 3 10 CB 2.5 3.5 5 DC 4 5 6 EC 2 2 2 FB 5 6 9 GG 1 7 9 HE, G 7 8 9 ID 2 3 4 JI 1 1.5 2 KH,J 2 2 2 LK 1 5 9 ML 7 8 9

103

likes
517 views

Answer to a math question For each of the following processes, determine whether in CPM or PERT: (1) Prepare a Network Diagram, (2) Determine the Different Routes and Indicate which is the Critical Path (3) Determine the Early and Late Start and End Times of each activity. (4) Determine the Slack of each Activity (5) Prepare a Gantt Chart (6) Indicate the Variance and Standard Deviation of the projects (7) Estimate the probability of meeting the desired times or the time for the desired probability Exercise 6 Probability 97% Activity Predecessor amb A - 1 1 1 BA 2 3 10 CB 2.5 3.5 5 DC 4 5 6 EC 2 2 2 FB 5 6 9 GG 1 7 9 HE, G 7 8 9 ID 2 3 4 JI 1 1.5 2 KH,J 2 2 2 LK 1 5 9 ML 7 8 9

Expert avatar
Adonis
4.4
106 Answers
To determine whether each process belongs to CPM or PERT:

(1) Prepare a Network Diagram: This process belongs to PERT as it involves probabilistic time estimates for activities.

(2) Determine the Different Routes and Indicate which is the Critical Path: This process belongs to CPM as it focuses on identifying the critical path based on deterministic time estimates.

(3) Determine the Early and Late Start and End Times of each activity: This process belongs to CPM as it involves calculating early start, late start, early end, and late end times based on deterministic estimates.

(4) Determine the Slack of each Activity: This process belongs to CPM as it calculates slack for each activity based on deterministic estimates.

(5) Prepare a Gantt Chart: This process belongs to CPM as it is used for scheduling and visualizing project tasks based on deterministic estimates.

(6) Indicate the Variance and Standard Deviation of the projects: This process belongs to PERT as it involves calculating variance and standard deviation for project completion time based on probabilistic estimates.

(7) Estimate the probability of meeting the desired times or the time for the desired probability: This process belongs to PERT as it uses probabilistic estimates to determine the probability of meeting project completion times.

Answer: All the processes except (6) Indicate the Variance and Standard Deviation of the projects belong to CPM.

Frequently asked questions (FAQs)
What is the area of a triangle if the base is 8 cm and the height is 12 cm?
+
What is the value of the adjacent side, given the hypotenuse is 10 and the angle is 45 degrees?
+
Math question: Graph the inequality 3x + 2y ≤ 10, where x and y are real numbers.
+
New questions in Mathematics
How to find the value of x and y which satisfy both equations x-2y=24 and 8x-y=117
Let f(x)=||x|−6|+|15−|x|| . Then f(6)+f(15) is equal to:
𝑦 = ( 𝑥2 − 3) (𝑥3 + 2 𝑥 + 1)
a ferry travels 1/6 of the distance between two ports in 3/7 hour. the ferry travels at a constant rate. at this rate, what fraction of the distance between the two ports can the ferry travel in one hour?
431414-1*(11111-1)-4*(5*3)
-11+29-18
Write 32/25 as a percent
solve the following trigo equation for 0°<= x <= 360°. sec x =-2
2.5 / 21.85
An electrical company manufactures batteries that have a duration that is distributed approximately normally, with a mean of 700 hours and a standard deviation of 40 hours. Find the probability that a randomly selected battery has an average life of less than 810 hours.
2x+4x=
Primes are numbers divisible only by 1 and themselves; There are infinitely many prime numbers and the first ones are 2, 3, 5, 7, 11, 13, 17, 19, 23, .... Consider a 12-sided die, with the faces numbered from 1 to 12. Out of 4 rolls, the probability that only the first three numbers are primes is:
Raúl, Gilberto and Arturo are playing golf; The probabilities of winning for each one are as follows: (Raúl wins) = 20% (Gilberto wins) = 0.05% (Arturo wins) = ¾%. Perform operations and order events from least to most probable.
A machine produces 255 bolts in 24 minutes. At the same rate, how many bolts would be produced in 40 minutes?
prove that for sets SS, AA, BB, and CC, where AA, BB, and CC are subsets of SS, the following equality holds: (A−B)−C=(A−C)−(B−C)
Write the inequality in the form of a<x<b. |x| < c^2
8. Measurement Jillian measured the distance around a small fish pond to be 27 yards. What would be a good estimate of the distance across the pond: 14 yards, 9 yards, or 7 yards? Explain how you decided.
4m - 3t + 7 = 16
6(k-7) -2=5
To apply a diagnostic test, in how many ways can 14 students be chosen out of 25? if the order does not matter