Question

For each of the following processes, determine whether in CPM or PERT: (1) Prepare a Network Diagram, (2) Determine the Different Routes and Indicate which is the Critical Path (3) Determine the Early and Late Start and End Times of each activity. (4) Determine the Slack of each Activity (5) Prepare a Gantt Chart (6) Indicate the Variance and Standard Deviation of the projects (7) Estimate the probability of meeting the desired times or the time for the desired probability Exercise 6 Probability 97% Activity Predecessor amb A - 1 1 1 BA 2 3 10 CB 2.5 3.5 5 DC 4 5 6 EC 2 2 2 FB 5 6 9 GG 1 7 9 HE, G 7 8 9 ID 2 3 4 JI 1 1.5 2 KH,J 2 2 2 LK 1 5 9 ML 7 8 9

103

likes
517 views

Answer to a math question For each of the following processes, determine whether in CPM or PERT: (1) Prepare a Network Diagram, (2) Determine the Different Routes and Indicate which is the Critical Path (3) Determine the Early and Late Start and End Times of each activity. (4) Determine the Slack of each Activity (5) Prepare a Gantt Chart (6) Indicate the Variance and Standard Deviation of the projects (7) Estimate the probability of meeting the desired times or the time for the desired probability Exercise 6 Probability 97% Activity Predecessor amb A - 1 1 1 BA 2 3 10 CB 2.5 3.5 5 DC 4 5 6 EC 2 2 2 FB 5 6 9 GG 1 7 9 HE, G 7 8 9 ID 2 3 4 JI 1 1.5 2 KH,J 2 2 2 LK 1 5 9 ML 7 8 9

Expert avatar
Adonis
4.4
104 Answers
To determine whether each process belongs to CPM or PERT:

(1) Prepare a Network Diagram: This process belongs to PERT as it involves probabilistic time estimates for activities.

(2) Determine the Different Routes and Indicate which is the Critical Path: This process belongs to CPM as it focuses on identifying the critical path based on deterministic time estimates.

(3) Determine the Early and Late Start and End Times of each activity: This process belongs to CPM as it involves calculating early start, late start, early end, and late end times based on deterministic estimates.

(4) Determine the Slack of each Activity: This process belongs to CPM as it calculates slack for each activity based on deterministic estimates.

(5) Prepare a Gantt Chart: This process belongs to CPM as it is used for scheduling and visualizing project tasks based on deterministic estimates.

(6) Indicate the Variance and Standard Deviation of the projects: This process belongs to PERT as it involves calculating variance and standard deviation for project completion time based on probabilistic estimates.

(7) Estimate the probability of meeting the desired times or the time for the desired probability: This process belongs to PERT as it uses probabilistic estimates to determine the probability of meeting project completion times.

Answer: All the processes except (6) Indicate the Variance and Standard Deviation of the projects belong to CPM.

Frequently asked questions (FAQs)
Math question: Find the derivative of f(x) = 3x^2 + 5√x + 8ln(x) - 7e^x.
+
What is the standard deviation of the following set of data: {3, 5, 7, 9, 11}?
+
Math Question: In circle O, if angle BOC = 120°, what is the measure of angle BAC?
+
New questions in Mathematics
2x-y=5 x-y=4
3(4×-1)-2(×+3)=7(×-1)+2
If f(x) = 3x 2, what is the value of x so that f(x) = 11?
what is the annual rate on ​$525 at 0.046​% per day for 3 months?
9b^2-6b-5
2.3/-71.32
A construction company is working on two projects: house construction and building construction. Each house requires 4 weeks of work and produces a profit of $50,000. Each building requires 8 weeks of work and produces a profit of $100,000. The company has a total of 24 work weeks available. Furthermore, it is known that at least 2 houses and at least 1 building must be built to meet the demand. The company wants to maximize its profits and needs to determine how many houses and buildings it should build to meet demand and maximize profits, given time and demand constraints.
According to a survey in a country 27% of adults do not own a credit card suppose a simple random sample of 800 adults is obtained . Describe the sampling distribution of P hat , the sample proportion of adults who do not own a credit card
solve for x 50x+ 120 (176-x)= 17340
The cost of unleaded gasoline in the Bay Area once followed an unknown distribution with a mean of $4.59 and a standard deviation of $0.10. Sixteen gas stations from the Bay Area are randomly chosen. We are interested in the average cost of gasoline for the 16 gas stations. 84. Find the probability that the average price for 30 gas stations is less than $4.55. a 0.6554 b 0.3446 c 0.0142 d 0.9858 e 0
In the telephone exchange of a certain university, calls come in at a rate of 5 every 2 minutes. Assuming a Poisson distribution, the average number of calls per second is: a) 1/8 b) 1/12 c) 1/10 d) 2/5 e) 1/24
A circular window has a rubber molding around the edge. If the window has a radius of 250 mm, how long is the piece of molding that is required ? (To the nearest mm)
0.1x8.2
If the regression equation is given by 4x –y + 5 = 0, then the slope of regression line of y on x is
Determine a general formula​ (or formulas) for the solution to the following equation.​ Then, determine the specific solutions​ (if any) on the interval [0,2π). cos30=0
Determine the Linear function whose graph passes through the points (6, -2) and has slope 3.
5a-3.(a-7)=-3
2p-6=8+5(p+9)
Mark is gluing a ribbon around the sides of a picture frame. The frame is 11 inches long and 7 includes wide. How much ribbon does Mark need?
x(squared) -8x=0