Question

For each of the following processes, determine whether in CPM or PERT: (1) Prepare a Network Diagram, (2) Determine the Different Routes and Indicate which is the Critical Path (3) Determine the Early and Late Start and End Times of each activity. (4) Determine the Slack of each Activity (5) Prepare a Gantt Chart (6) Indicate the Variance and Standard Deviation of the projects (7) Estimate the probability of meeting the desired times or the time for the desired probability Exercise 6 Probability 97% Activity Predecessor amb A - 1 1 1 BA 2 3 10 CB 2.5 3.5 5 DC 4 5 6 EC 2 2 2 FB 5 6 9 GG 1 7 9 HE, G 7 8 9 ID 2 3 4 JI 1 1.5 2 KH,J 2 2 2 LK 1 5 9 ML 7 8 9

103

likes
517 views

Answer to a math question For each of the following processes, determine whether in CPM or PERT: (1) Prepare a Network Diagram, (2) Determine the Different Routes and Indicate which is the Critical Path (3) Determine the Early and Late Start and End Times of each activity. (4) Determine the Slack of each Activity (5) Prepare a Gantt Chart (6) Indicate the Variance and Standard Deviation of the projects (7) Estimate the probability of meeting the desired times or the time for the desired probability Exercise 6 Probability 97% Activity Predecessor amb A - 1 1 1 BA 2 3 10 CB 2.5 3.5 5 DC 4 5 6 EC 2 2 2 FB 5 6 9 GG 1 7 9 HE, G 7 8 9 ID 2 3 4 JI 1 1.5 2 KH,J 2 2 2 LK 1 5 9 ML 7 8 9

Expert avatar
Adonis
4.4
95 Answers
To determine whether each process belongs to CPM or PERT:

(1) Prepare a Network Diagram: This process belongs to PERT as it involves probabilistic time estimates for activities.

(2) Determine the Different Routes and Indicate which is the Critical Path: This process belongs to CPM as it focuses on identifying the critical path based on deterministic time estimates.

(3) Determine the Early and Late Start and End Times of each activity: This process belongs to CPM as it involves calculating early start, late start, early end, and late end times based on deterministic estimates.

(4) Determine the Slack of each Activity: This process belongs to CPM as it calculates slack for each activity based on deterministic estimates.

(5) Prepare a Gantt Chart: This process belongs to CPM as it is used for scheduling and visualizing project tasks based on deterministic estimates.

(6) Indicate the Variance and Standard Deviation of the projects: This process belongs to PERT as it involves calculating variance and standard deviation for project completion time based on probabilistic estimates.

(7) Estimate the probability of meeting the desired times or the time for the desired probability: This process belongs to PERT as it uses probabilistic estimates to determine the probability of meeting project completion times.

Answer: All the processes except (6) Indicate the Variance and Standard Deviation of the projects belong to CPM.

Frequently asked questions (FAQs)
What is the limit of (3x^2 - 2x + 1) / (2x - 1) as x approaches 2?
+
What is the discriminant of the cubic function f(x) = x^3?
+
Math question: Solve the inequality 3x + 5 > 17 for x.
+
New questions in Mathematics
Using a remarkable product you must factor the expression: f(x) =36x^2-324 and you are entitled to 5 steps
The gross domestic product the gdp for the United States in 2017 was approximately $2.05x10^3. If you wrote this number in standard notation , it would be 205 followed by how many zeros
2.5 / 21.85
(5u + 6)-(3u+2)=
Solve this mathematical problem if 3/5 of a roll of tape measures 2m. How long is the complete roll?
Find the derivatives for y=X+1/X-1
78 percent to a decimal
The durability of a tire of a certain brand is a Normal random variable with an average of 64,000 km and a standard deviation of 9,000 km. Assuming independence between tires, what is the probability that the 4 tires on a car will last more than 58,000 km?
A test has 5 multiple choice questions. Each question has 4 alternatives, only one of which is correct. A student who did not study for the test randomly chooses one alternative for each question.(a) What is the probability of him getting a zero on the test?(b) What is the probability of him getting a three or more? The maximum mark for the test is 5, with each question worth one point.
calculate the area in square units of A rectangle with length 6cm and breadth 5cm
Use the power rule for logarithms to solve the following word problem exactly. If you invest $1, 000 at 5% interest compounded annually, how many years will it take before you have $2,000?
Find the minimum value of the function y = -4 x3 + 60 x2 -252 x + 8 for values of x between x = 0 and x = 9 Enter the value of the function, not the value of x
MAKING AN ARGUMENT You use synthetic division to divide f(x) by (x βˆ’ a) and find that the remainder equals 15. Your friend concludes that f (15) = a. Is your friend correct? Explain your reasoning.
ind the z-score for which 72% of the distribution's area lies between -z and z. -1.7417, 1.7417 -1.1538, 1.1538 -1.0803, 1.0803 -2.826, 2.826
Given a circle π‘˜(𝑆; π‘Ÿ = 4 π‘π‘š) and a line |𝐴𝐡| = 2 π‘π‘š. Determine and construct the set of all centers of circles that touch circle π‘˜ and have radius π‘Ÿ = |𝐴𝐡|
What is the percentage of nitrogen abundance in copper dinatrate Cu(NO3)2
did an analysis of dropout from the nursing faculty at the Universidad Veracruzana. With a poblation of 122 students, it turned out that according to the gender data, the female sex predominates with 82%, and the male sex male is found with 12%. The main factors why students drop out are, first of all, "Not "re-enrolled" at 49%, second place "Personal reasons" at 20%, third place "change of school" in 11%, "lack of documents" and "economic reasons" in 7%, change of residence and lack of social service in 3%. Of this sample, how many students dropped out for other reasons?
the length of the fenced in area is to be 5 ft greater than the width and the total amount of fencing to be used is 89 ft find the width and length
Sin(5pi/3)
12[4 + (8 + 7) + 5]