Question

For each of the following processes, determine whether in CPM or PERT: (1) Prepare a Network Diagram, (2) Determine the Different Routes and Indicate which is the Critical Path (3) Determine the Early and Late Start and End Times of each activity. (4) Determine the Slack of each Activity (5) Prepare a Gantt Chart (6) Indicate the Variance and Standard Deviation of the projects (7) Estimate the probability of meeting the desired times or the time for the desired probability Exercise 6 Probability 97% Activity Predecessor amb A - 1 1 1 BA 2 3 10 CB 2.5 3.5 5 DC 4 5 6 EC 2 2 2 FB 5 6 9 GG 1 7 9 HE, G 7 8 9 ID 2 3 4 JI 1 1.5 2 KH,J 2 2 2 LK 1 5 9 ML 7 8 9

103

likes
517 views

Answer to a math question For each of the following processes, determine whether in CPM or PERT: (1) Prepare a Network Diagram, (2) Determine the Different Routes and Indicate which is the Critical Path (3) Determine the Early and Late Start and End Times of each activity. (4) Determine the Slack of each Activity (5) Prepare a Gantt Chart (6) Indicate the Variance and Standard Deviation of the projects (7) Estimate the probability of meeting the desired times or the time for the desired probability Exercise 6 Probability 97% Activity Predecessor amb A - 1 1 1 BA 2 3 10 CB 2.5 3.5 5 DC 4 5 6 EC 2 2 2 FB 5 6 9 GG 1 7 9 HE, G 7 8 9 ID 2 3 4 JI 1 1.5 2 KH,J 2 2 2 LK 1 5 9 ML 7 8 9

Expert avatar
Adonis
4.4
105 Answers
To determine whether each process belongs to CPM or PERT:

(1) Prepare a Network Diagram: This process belongs to PERT as it involves probabilistic time estimates for activities.

(2) Determine the Different Routes and Indicate which is the Critical Path: This process belongs to CPM as it focuses on identifying the critical path based on deterministic time estimates.

(3) Determine the Early and Late Start and End Times of each activity: This process belongs to CPM as it involves calculating early start, late start, early end, and late end times based on deterministic estimates.

(4) Determine the Slack of each Activity: This process belongs to CPM as it calculates slack for each activity based on deterministic estimates.

(5) Prepare a Gantt Chart: This process belongs to CPM as it is used for scheduling and visualizing project tasks based on deterministic estimates.

(6) Indicate the Variance and Standard Deviation of the projects: This process belongs to PERT as it involves calculating variance and standard deviation for project completion time based on probabilistic estimates.

(7) Estimate the probability of meeting the desired times or the time for the desired probability: This process belongs to PERT as it uses probabilistic estimates to determine the probability of meeting project completion times.

Answer: All the processes except (6) Indicate the Variance and Standard Deviation of the projects belong to CPM.

Frequently asked questions (FAQs)
Question: In ΔABC, if ∠A ≅ ∠B and AB ≅ AC, prove that BC ≅ AC.
+
What is the area of a circle with a radius of 8 inches?
+
What is the variance of the dataset 4, 5, 7, 8, 9, 10?
+
New questions in Mathematics
The director of a company must transfer 6 people from the human resources department to the sales department, in order to sustain sales during the month of December. What is the probability that he will transfer only 2 of them?
2x-4y=-6; -4y+4y=-8
A soft drink machine outputs a mean of 23 ounces per cup. The machines output is normally distributed with a standard deviation of 3 ounces. What is the probability of filling a cup between 26 and 28 ounces round your answer to four decimal places
A job takes 9 workers 92 hours to finish. How many hours would it take 5 workers to complete the same job?
A test has 5 multiple choice questions. Each question has 4 alternatives, only one of which is correct. A student who did not study for the test randomly chooses one alternative for each question.(a) What is the probability of him getting a zero on the test?(b) What is the probability of him getting a three or more? The maximum mark for the test is 5, with each question worth one point.
In the telephone exchange of a certain university, calls come in at a rate of 5 every 2 minutes. Assuming a Poisson distribution, the average number of calls per second is: a) 1/8 b) 1/12 c) 1/10 d) 2/5 e) 1/24
Use linear approximation to estimate the value of the sine of 31o.
X³-27
Quadratic equation 2X = 15/X + 7
A contractor gives a bank note for $10250 at a rate of 1% for one month. How much interest is charged for 4 months?
factor the polynomial completely over the set of complex numbers b(x)=x^4-2x^3-17x^2+4x+30
Let N be the total number of ways to choose at least one ride, out of a total of 7 different ones, existing in an amusement park. Can it be said that N is a natural number equal to?
a) Statistics scores are normally distributed with the mean of 75 and standard deviation of 7. What is the probability that a student scores between 80 and 88
Oi👋🏻 Toque em "Criar Nova Tarefa" para enviar seu problema de matemática. Um dos nossos especialistas começará a trabalhar nisso imediatamente!
x²-7x+12=0
The following incoming payments show up at a tax inspection: 25 000€ on 19.01.2008, 140 000€ on 27.03.2008 and 19 000€ on a date that which is illegible, and 60 000€ on 15.06.2008. On which date did the payment of the 19 000€ appear, if on 30.06.2008 the money on the account (incl. interest at 4%) is 246 088.89€? Use simple interest and 30E/360 DCC. Solution: 45 days, 15.05.08
7-1=6 6x2=12 Explain that
A triangle is cut by a line s parallel to the base in such a way that it divides the side of the triangle into parts in the ratio of 2 : 3. Find the other side of the triangle if it is known that the line s divides it into parts whose length is 5 cm.
Mark is gluing a ribbon around the sides of a picture frame. The frame is 11 inches long and 7 includes wide. How much ribbon does Mark need?
13/25+7/16